LUI KIN WAI v. ACTIVE ENGINEERING LTD AND ANOTHER
On the balance of probabilities the court was not satisfied that the plaintiff fell from the platform as alleged; contemporaneous hospital records and the plaintiff's statement indicated a fall down stairs, and the plaintiff's credibility was undermined by inconsistent accounts. Therefore the plaintiff failed to discharge the burden of proof and the action is dismissed; alternatively, if the fall occurred as recorded, it was caused by the plaintiff's own lack of care and did not establish defendants' negligence.
- Citation
- LUI KIN WAI v. ACTIVE ENGINEERING LTD AND ANOTHER
- Parties
- Plaintiff: LUI KIN WAI; 1st Defendant: ACTIVE ENGINEERING LIMITED; 2nd Defendant: LUI TSUN LUNG and LUI MAN TO trading as YUEN HING ENGINEERING COMPANY
- Court
- District Court
- Jurisdiction
- Hong Kong
- Judgment Date
- 12 November 2009
- Case Number
- DCPI594/2008
- Procedural Posture
- Personal Injuries Action / Judgment (trial)
- Outcome
- Action dismissed
- Legal Topics
- Slip and Fall, Duty of Care, Causation, Damages, Witness Credibility
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
LUI KIN WAI
Plaintiff
ACTIVE ENGINEERING LIMITED
1st Defendant
LUI TSUN LUNG and LUI MAN TO trading as YUEN HING ENGINEERING COMPANY
2nd Defendant
Procedural Posture
Personal Injuries Action / Judgment (trial)
Legal Issues
- 1 Whether the plaintiff fell from the 6 m platform as alleged
- 2 If so, whether the accident was caused by breach of duty by the defendants
- 3 Quantum of damages if liability established
Ratio Decidendi
On the balance of probabilities the court was not satisfied that the plaintiff fell from the platform as alleged; contemporaneous hospital records and the plaintiff's statement indicated a fall down stairs, and the plaintiff's credibility was undermined by inconsistent accounts. Therefore the plaintiff failed to discharge the burden of proof and the action is dismissed; alternatively, if the fall occurred as recorded, it was caused by the plaintiff's own lack of care and did not establish defendants' negligence.
Court Disposition
Action dismissed
Orders
- Action dismissed
- An order nisi that the costs of the action are to be paid by Mr. Lui to Active Engineering Limited and Yuen Hing Engineering Company, with Certificate for Counsel, to be taxed if not agreed
Full Case Text
Judgment text and source record