HEADWIN ENGINEERING LTD v. UNITED SOUNDFAIR ENGINEERING CO LTD
The Signed R4 Quotation constituted the contract; its express Condition made the sub-contract a fixed price lump sum contract not subject to re-measurement; the Priced BQ and addenda to the employer's sub-contract did not alter that contract; plaintiff was entitled to the unpaid balance (net) of the lump sum and to...
Source-derived case information.
- Citation
- HEADWIN ENGINEERING LTD v. UNITED SOUNDFAIR ENGINEERING CO LTD
- Parties
- Plaintiff: Plaintiff; Defendant: Defendant
- Court
- District Court
- Jurisdiction
- Hong Kong
- Judgment Date
- 9 April 2008
- Case Number
- DCCJ5034/2006
- Procedural Posture
- Construction Contract Dispute (claimed Payment and Counterclaim) / District Court Judgment (trial Concluded)
- Outcome
- Judgment for the Plaintiff for HK$564,500.00 (outstanding contract balance and variation cost). Defendant's counterclaim dismissed. Costs awarded to Plaintiff (costs nisi to be taxed if not agreed).
- Legal Topics
- Lump Sum Contract, Variation of Contract, Warranty Obligations, Bill of Quantities, Contract Interpretation, Remedial Works, Re Measurement and Valuation
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Plaintiff
Plaintiff
Defendant
Defendant
Procedural Posture
Construction Contract Dispute (claimed Payment and Counterclaim) / District Court Judgment (trial Concluded)
Legal Issues
- 1 Whether the contract between the parties was the Signed R4 Quotation or comprised the Four Documents
- 2 Whether the Priced Bill of Quantities and/or the Particular Specifications formed part of the contract
- 3 Whether the Steelworks were on fixed price lump sum basis or on a discount/with-quantities re-measurement basis
Ratio Decidendi
The Signed R4 Quotation constituted the contract; its express Condition made the sub-contract a fixed price lump sum contract not subject to re-measurement; the Priced BQ and addenda to the employer's sub-contract did not alter that contract; plaintiff was entitled to the unpaid balance (net) of the lump sum and to payment for variation works; defendant's counterclaim failed.
Court Disposition
Judgment for the Plaintiff for HK$564,500.00 (outstanding contract balance and variation cost). Defendant's counterclaim dismissed. Costs awarded to Plaintiff (costs nisi to be taxed if not agreed).
Orders
- Defendant to pay Plaintiff HK$564,500.00
- Defendant to pay Plaintiff costs of the action (including costs of the counterclaim and reserved costs if any) to be taxed if not agreed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment