LAI TING KWONG v. WUI LOONG SCAFFOLDING WORKS CO LTD
Clause 6 was ambiguous and construed not to make time of payment essential; one-day late payment did not entitle plaintiff to terminate; plaintiff repudiated by ceasing work from 27 Dec 2013 so forfeited retention; plaintiff was nonetheless entitled to the assessed 4th interim payment of $143,487; defendant entitled to recover part of day-worker costs leading to judgment for defendant $22,832; net award payable to plaintiff $120,655 plus interest and costs nisi.
- Citation
- LAI TING KWONG v. WUI LOONG SCAFFOLDING WORKS CO LTD
- Parties
- Plaintiff: Plaintiff; Defendant: Defendant
- Court
- District Court
- Jurisdiction
- Hong Kong
- Judgment Date
- 17 February 2017
- Case Number
- DCCJ1748/2014
- Procedural Posture
- Contract Dispute (scaffolding Subcontract) / Trial Judgment (deputy District Judge)
- Outcome
- Judgment for defendant on its re-amended counterclaim in the sum of $22,832; judgment for plaintiff on his counterclaim to counterclaim in the sum of $143,487; after set-off defendant to pay plaintiff net sum $120,655 with interest; costs nisi in favour of plaintiff.
- Legal Topics
- Time of the Essence, Termination for Breach, Retention Money, Repudiatory Breach, Implied Terms, Set Off, Voluntary Payment/recovery, Assessment of Damages
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Plaintiff
Plaintiff
Defendant
Defendant
Procedural Posture
Contract Dispute (scaffolding Subcontract) / Trial Judgment (deputy District Judge)
Legal Issues
- 1 Whether time for payment was of the essence permitting termination for one-day late payment
- 2 Whether plaintiff validly terminated the subcontract and was entitled to damages including loss of profit and retention money
- 3 Whether plaintiff was in repudiatory breach by ceasing work
Ratio Decidendi
Clause 6 was ambiguous and construed not to make time of payment essential; one-day late payment did not entitle plaintiff to terminate; plaintiff repudiated by ceasing work from 27 Dec 2013 so forfeited retention; plaintiff was nonetheless entitled to the assessed 4th interim payment of $143,487; defendant entitled to recover part of day-worker costs leading to judgment for defendant $22,832; net award payable to plaintiff $120,655 plus interest and costs nisi.
Court Disposition
Judgment for defendant on its re-amended counterclaim in the sum of $22,832; judgment for plaintiff on his counterclaim to counterclaim in the sum of $143,487; after set-off defendant to pay plaintiff net sum $120,655 with interest; costs nisi in favour of plaintiff.
Orders
- Judgment for defendant against plaintiff in the sum of 22832 HKD
- Judgment for plaintiff on counterclaim to counterclaim in the sum of 143487 HKD
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment