LIU KEITH CHE MING AND ANOTHER v. POON CHI SING t/a GOOD VIEW ORNAMENT
The court found the contract was a build/procurement contract based on the parties' quotations; the joint single expert established a number of defects attributable to the defendant's workmanship. The court accepted substantially the expert's valuation of remedial work but applied abatements for matters the...
Source-derived case information.
- Citation
- LIU KEITH CHE MING AND ANOTHER v. POON CHI SING t/a GOOD VIEW ORNAMENT
- Parties
- 1st Plaintiff: LIU KEITH CHE MING; 2nd Plaintiff: CHAN PO YEE IDA; Defendant: POON CHI SING trading as GOOD VIEW ORNAMENT
- Court
- District Court
- Jurisdiction
- Hong Kong
- Judgment Date
- 8 February 2013
- Case Number
- DCCJ2421/2010
- Procedural Posture
- Civil Action Renovation Contract Dispute / Judgment Delivered 8 February 2013
- Outcome
- Plaintiffs' claim partly allowed in respect of certain remedial contributions; defendant's counterclaim allowed and set off against award; net judgment in favour of defendant for HKD 86,978.99; interest and costs awarded.
- Legal Topics
- Defective Workmanship, Delay and Causation, Quantum of Damages, Counterclaim and Set Off, Expert Evidence, Mitigation of Loss
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
LIU KEITH CHE MING
1st Plaintiff
CHAN PO YEE IDA
2nd Plaintiff
POON CHI SING trading as GOOD VIEW ORNAMENT
Defendant
Procedural Posture
Civil Action Renovation Contract Dispute / Judgment Delivered 8 February 2013
Legal Issues
- 1 Scope of the contractor's obligations under the quotations and subsequent amendments
- 2 Whether the renovation work was defective and attributable to the defendant
- 3 Whether there was delay and, if so, whether it was caused by the defendant or by plaintiffs/third parties
Ratio Decidendi
The court found the contract was a build/procurement contract based on the parties' quotations; the joint single expert established a number of defects attributable to the defendant's workmanship. The court accepted substantially the expert's valuation of remedial work but applied abatements for matters the defendant reasonably raised and for plaintiff failures to mitigate and allowed specific contributions to rectification totalling HKD 62,151.01. The defendant's counterclaim for the outstanding contract balance was allowed and set off against the award, resulting in a net judgment on the counterclaim of HKD 86,978.99. Interest and costs were awarded accordingly.
Court Disposition
Plaintiffs' claim partly allowed in respect of certain remedial contributions; defendant's counterclaim allowed and set off against award; net judgment in favour of defendant for HKD 86,978.99; interest and costs awarded.
Orders
- Award to plaintiffs for contribution to remedial works as assessed and allowed by the court totalling HKD 62,151.01 (subject to set off)
- Allow defendant's counterclaim for outstanding contract balance and set off against plaintiffs' award leaving judgment on counterclaim of HKD 86,978.99 for the defendant
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment