SAN FAI CONSTRUCTION & DECORATION ENGINEERING LTD v. TSANG, FUSON

SAN FAI CONSTRUCTION & DECORATION ENGINEERING LTD v. TSANG, FUSON

Contemporaneous correspondence and conduct established that San Fai had substantially completed the works by early 2003 and the maintenance/payment period commenced then; Tsang failed to prove the alleged defects or their causation and therefore could not withhold payment or succeed in counterclaim; plaintiff...

Source-derived case information.

Citation
SAN FAI CONSTRUCTION & DECORATION ENGINEERING LTD v. TSANG, FUSON
Parties
Plaintiff: San Fai; Defendant: Tsang
Court
District Court
Jurisdiction
Hong Kong
Judgment Date
1 February 2008
Case Number
DCCJ3133/2004
Procedural Posture
Construction Contract Claim / Judgment
Outcome
Judgment for Plaintiff
Legal Topics
Substantial Performance, Defects, Payment on Completion, Counterclaim, Damages, Interest, Costs
Source Language
en
Contract Law Construction Law Civil Procedure Substantial Performance Defects Payment on Completion Counterclaim Damages +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

San Fai

Plaintiff

Tsang

Defendant

Procedural Posture

Construction Contract Claim / Judgment

  1. 1 Whether the contractor completed the works
  2. 2 Whether the works were defective and causation of alleged defects
  3. 3 Whether plaintiff was entitled to the balance of the contract sum and its amount

Ratio Decidendi

Contemporaneous correspondence and conduct established that San Fai had substantially completed the works by early 2003 and the maintenance/payment period commenced then; Tsang failed to prove the alleged defects or their causation and therefore could not withhold payment or succeed in counterclaim; plaintiff entitled to the unpaid balance with interest and costs.

Court Disposition

Judgment for Plaintiff

Orders

  • Judgment for the Plaintiff in the sum of HK$81,350
  • Interest on HK$81,350 at 1% above HSBC prime rate from date of writ to date of judgment and thereafter at the judgment rate until full payment