CITY TOP ENGINEERING LTD. v. LEE SHING YUE CONSTRUCTION CO. LTD.
Security for costs was refused against City Top Engineering Limited because the court found CT's finances had improved, it remained a going concern, its claim was bona fide with prospects of success and ordering security would likely shut it out and cause injustice; security was ordered against Kingpoint Profits Limited in HCA13906/1999 in the sum of HKD 600,000 because KP is a foreign plaintiff and a financial backer of CT, creating enforcement risk and justifying partial protection to defendants.
- Citation
- CITY TOP ENGINEERING LTD. v. LEE SHING YUE CONSTRUCTION CO. LTD.
- Parties
- Plaintiff (also 2nd Plaintiff in Hca13906/1998): City Top Engineering Limited; 1st Plaintiff (foreign Plaintiff, Co Plaintiff and Financial Backer): Kingpoint Profits Limited; Defendant (1st Defendant in Hca13906/1998): Lee Shing Yue Construction Company Limited; 2nd Defendant (in Hca13906/1998): Thomas Lee Chun Cheong
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 28 February 2000
- Case Number
- HCCT75/1998
- Procedural Posture
- Construction and Arbitration Proceedings With Interlocutory Applications / Interlocutory Hearing for Security for Costs (judgment in Chambers)
- Outcome
- Interlocutory orders: security for costs ordered against Kingpoint Profits Limited in HCA13906/1999 for HKD 600,000; summons for security for costs against City Top Engineering Limited in HCCT75/1998 dismissed; costs orders made.
- Legal Topics
- Security for Costs, Impecuniosity, Foreign Plaintiff, Companies Ordinance S.357, Order 23 Rule 1
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
City Top Engineering Limited
Plaintiff (also 2nd Plaintiff in Hca13906/1998)
Kingpoint Profits Limited
1st Plaintiff (foreign Plaintiff, Co Plaintiff and Financial Backer)
Lee Shing Yue Construction Company Limited
Defendant (1st Defendant in Hca13906/1998)
Thomas Lee Chun Cheong
2nd Defendant (in Hca13906/1998)
Procedural Posture
Construction and Arbitration Proceedings With Interlocutory Applications / Interlocutory Hearing for Security for Costs (judgment in Chambers)
Legal Issues
- 1 Whether security for costs should be ordered against City Top Engineering Limited under s.357 Companies Ordinance
- 2 Whether security for costs should be ordered against Kingpoint Profits Limited as a foreign plaintiff under Order 23 r.1
- 3 Quantum of any security to be ordered
Ratio Decidendi
Security for costs was refused against City Top Engineering Limited because the court found CT's finances had improved, it remained a going concern, its claim was bona fide with prospects of success and ordering security would likely shut it out and cause injustice; security was ordered against Kingpoint Profits Limited in HCA13906/1999 in the sum of HKD 600,000 because KP is a foreign plaintiff and a financial backer of CT, creating enforcement risk and justifying partial protection to defendants.
Court Disposition
Interlocutory orders: security for costs ordered against Kingpoint Profits Limited in HCA13906/1999 for HKD 600,000; summons for security for costs against City Top Engineering Limited in HCCT75/1998 dismissed; costs orders made.
Orders
- Kingpoint Profits Limited to pay into court HKD 600,000 as security for costs in HCA13906/1999
- Summons dated 18 November 1999 (HCCT75/1998) seeking security for costs against City Top Engineering Limited dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment