S Co v. B Co
The court held that the tribunal had jurisdiction over both the Balance Payment Claim and the S III Contract Claim because those disputes arose in the course of performance of the Cooperation Agreement and were properly referable under the Arbitration Clause; the tribunal's jurisdictional ruling was made in an award on the merits and therefore the correct challenge route was under Article 34; judicial review is de novo but confined to true questions of jurisdiction and should avoid merits review; S Co waived procedural objections by participation; accordingly both Article 16 and Article 34 applications were dismissed and costs awarded to B Co on an indemnity basis with certificates for...
- Citation
- S Co v. B Co
- Parties
- Plaintiff (respondent in the Arbitration): S Co; Defendant (claimant in the Arbitration): B Co
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 24 July 2014
- Case Number
- HCCT12/2013
- Procedural Posture
- Construction and Arbitration Proceedings / Decision (setting Aside Applications)
- Outcome
- Both the Article 16(3) and Article 34 applications dismissed
- Legal Topics
- Setting Aside Arbitral Award, Jurisdiction (competence Competence), Model Law Articles 16 and 34, Waiver and Estoppel, Costs
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
S Co
Plaintiff (respondent in the Arbitration)
B Co
Defendant (claimant in the Arbitration)
Procedural Posture
Construction and Arbitration Proceedings / Decision (setting Aside Applications)
Legal Issues
- 1 Whether the arbitral tribunal had jurisdiction over the Balance Payment Claim and the S III Contract Claim
- 2 Whether the award deals with disputes outside the submission to arbitration or beyond the tribunal's scope
- 3 Whether S Co was unable to present its case
Ratio Decidendi
The court held that the tribunal had jurisdiction over both the Balance Payment Claim and the S III Contract Claim because those disputes arose in the course of performance of the Cooperation Agreement and were properly referable under the Arbitration Clause; the tribunal's jurisdictional ruling was made in an award on the merits and therefore the correct challenge route was under Article 34; judicial review is de novo but confined to true questions of jurisdiction and should avoid merits review; S Co waived procedural objections by participation; accordingly both Article 16 and Article 34 applications were dismissed and costs awarded to B Co on an indemnity basis with certificates for...
Court Disposition
Both the Article 16(3) and Article 34 applications dismissed
Orders
- Article 16 originating summons dismissed with costs to B Co on an indemnity basis with certificate for two counsel
- Article 34 originating summons dismissed with costs to B Co on an indemnity basis with certificate for two counsel
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment