CHUN WO FOUNDATIONS LTD v. DORRO PROPERTIES LTD

CHUN WO FOUNDATIONS LTD v. DORRO PROPERTIES LTD

The court upheld the trial judge's findings that the plaintiff had substantially completed the piling by 31 January 2000 and had satisfied contractual/Building Authority submission obligations; the ALA survey did not establish a causal link between any alleged out-of-tolerance piles and subsequent pile cap design...

Source-derived case information.

Citation
CHUN WO FOUNDATIONS LTD v. DORRO PROPERTIES LTD
Parties
Plaintiff/respondent: Chun Wo Foundations Limited; Defendant/appellant: Dorro Properties Limited
Court
Court of Appeal
Jurisdiction
Hong Kong
Judgment Date
26 July 2006
Case Number
CACV293/2005
Procedural Posture
Civil Appeal (construction/contract) / Court of Appeal Judgment on Appeal From HCCT No.84 of 2000
Outcome
Appeal dismissed; judgment below affirmed in favour of the plaintiff/respondent
Legal Topics
Substantial Completion, Time at Large, Liquidated Damages, Defective Works, Pile Tolerances, Causation and Proof of Damage, Contractual Records and Certification
Source Language
en
Contract Construction Law Building Regulation Commercial Law Substantial Completion Time at Large Liquidated Damages Defective Works +3 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Chun Wo Foundations Limited

Plaintiff/respondent

Dorro Properties Limited

Defendant/appellant

Procedural Posture

Civil Appeal (construction/contract) / Court of Appeal Judgment on Appeal From HCCT No.84 of 2000

  1. 1 Whether the contractor completed the works within the contractual/reasonable time
  2. 2 Whether the as-built piles were out of contractual tolerance and thus defective
  3. 3 Whether any alleged defect caused damage or delay for which the contractor is liable

Ratio Decidendi

The court upheld the trial judge's findings that the plaintiff had substantially completed the piling by 31 January 2000 and had satisfied contractual/Building Authority submission obligations; the ALA survey did not establish a causal link between any alleged out-of-tolerance piles and subsequent pile cap design amendments or delay; the extensive delay before superstructure works was attributable to the defendant's actions and circumstances, and the defendant failed to prove damage causally caused by the plaintiff, therefore the defendant's counterclaim and appeal fail.

Court Disposition

Appeal dismissed; judgment below affirmed in favour of the plaintiff/respondent

Orders

  • Appeal dismissed
  • Order nisi for costs in favour of the plaintiff/respondent