SUNLEY ENGINEERING & CONSTRUCTION CO LTD v. NGO KEE CONSTRUCTION CO LTD

SUNLEY ENGINEERING & CONSTRUCTION CO LTD v. NGO KEE CONSTRUCTION CO LTD

The sub-contract incorporated the bills of quantities so Sunley was entitled to recover for variations for works omitted or understated where those works were necessary to complete the contracted scope; Sunley was entitled to the quantified variations (subject to agreed deductions for proven contra-charges) and Ngo...

Source-derived case information.

Citation
SUNLEY ENGINEERING & CONSTRUCTION CO LTD v. NGO KEE CONSTRUCTION CO LTD
Parties
Plaintiff: Sunley Engineering & Construction Co. Ltd.; Defendant: Ngo Kee Construction Company Ltd.
Court
Court of First Instance
Jurisdiction
Hong Kong
Judgment Date
13 December 2006
Case Number
HCCT49/2002
Procedural Posture
Construction and Arbitration Proceedings / Judgment of the Court of First Instance
Outcome
Judgment for the Plaintiff (Sunley Engineering & Construction Co. Ltd.). Defendant's counterclaim largely dismissed except for limited contra-charges.
Legal Topics
Variations, Contra Charges, Retention Money, Delay Counterclaim, Admissibility of Evidence, Expert Evidence, Quantum Assessment, Mark Up on Variations
Source Language
en
Construction Law Contract Law Civil Evidence Building Regulation Compliance Delay and Damages Variations Contra Charges Retention Money +5 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 2 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Sunley Engineering & Construction Co. Ltd.

Plaintiff

Ngo Kee Construction Company Ltd.

Defendant

Procedural Posture

Construction and Arbitration Proceedings / Judgment of the Court of First Instance

  1. 1 Whether additional works (cart away, coring, site investigations, hoarding, additional H-piles, pre-boring, pile caps, loading tests, design works, Maunsell fee) constituted variations under the sub-contract
  2. 2 Appropriate quantum and mark-up for admitted/established variations
  3. 3 Whether specified contra-charges (including remedial backfilling and rockfill plug) were recoverable against Sunley

Ratio Decidendi

The sub-contract incorporated the bills of quantities so Sunley was entitled to recover for variations for works omitted or understated where those works were necessary to complete the contracted scope; Sunley was entitled to the quantified variations (subject to agreed deductions for proven contra-charges) and Ngo Kee failed to prove that Sunley caused delay to the main contract or resulting loss, accordingly Ngo Kee's major delay counterclaim failed and judgment was entered for Sunley in the net sum of HK$6,843,309 with interest at prime plus 1% from 21 June 2001; PNAP 227 is recommendatory and the rockfill plug was not within Sunley's scope and retention must be released.

Court Disposition

Judgment for the Plaintiff (Sunley Engineering & Construction Co. Ltd.). Defendant's counterclaim largely dismissed except for limited contra-charges.

Orders

  • Judgment for Sunley Engineering & Construction Co. Ltd. in the sum of HK$6,843,309
  • Interest on the judgment at prime plus 1% running from 21 June 2001; interest computed to 30 November 2006 as HK$2,571,583 and thereafter at daily rate HK$1,687 until judgment and thereafter at judgment rate