TECH-TRANS SYSTEM LTD v. ELM COMPUTER TECHNOLOGIES LTD

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The Court found no evidence Ocean rejected the goods; the alleged oral delivery-only-on-request term was either inadmissible as contradicting the written contract or was beyond the agent's authority; the maintenance period issue was a breach of warranty under s.55(1) and did not permit rejection; the signed quotation by Tech-Trans Telecom made it party to the contract; accordingly TT System's claim failed and ELM succeeded on its counterclaim against Tech-Trans Telecom for US$98,641.86 plus interest.

Court disposition

Claim by Tech-Trans System Limited dismissed; counterclaim by ELM Computer Technologies Limited allowed against Tech-Trans Telecom Limited.

Orders

  • Judgment for ELM Computer Technologies Limited against Tech-Trans Telecom Limited in the sum of US$98,641.86 with interest at judgment rate from 12 April 2005 until satisfaction.
  • Order nisi to be made absolute in 14 days: (1) costs in the original action to be borne by Tech-Trans System Limited, to be taxed if not agreed, with certificate for Counsel; (2) ELM to bear the costs of the counterclaim against Tech-Trans System Limited, to be taxed if not agreed, with certificate for Counsel; (3) Tech-Trans Telecom Limited to pay to ELM the costs of the counterclaim, to be taxed if not agreed, with certificate for Counsel.

02

Material facts

Parties

Tech-Trans System Limited

Plaintiff (original Action); Defendant (by Counterclaim) Counsel: Mr. Jenkin Suen

ELM Computer Technologies Limited

Defendant (original Action); Plaintiff (by Counterclaim) Counsel: Mr. Jonathan Chang

Tech-Trans Telecom Limited

Defendant (by Counterclaim) Counsel: Mr. Jenkin Suen

Amounts and remedies

  • Claimed Loss of Profit (sub Sale): HKD 70,809.5
  • ELM Counterclaim Judgment Amount: USD 98,641.86
  • Ocean Deposit Referenced: HKD 420,108

03

Procedural history

  1. Posture

    Civil: Sale of Goods and Contract Dispute / Judgment (district Court)

04

Questions and positions

Legal issues

Party arguments

Applicant
Tech-Trans System alleged loss of profit of HK$70,809.50 because Ocean rejected the sub-sale; argued delivery occurred without instruction and maintenance period commenced early, justifying rejection and damages.
Respondent
ELM contended contract was with Tech-Trans Telecom which accepted and received delivery; Martin Yung lacked authority to bind ELM to the alleged oral delivery restriction; under s.55(1) Sales of Goods Ordinance insufficient maintenance is a breach of warranty not a condition so buyer cannot reject; Ocean accepted the goods and ELM claimed US$98,641.86 plus interest.

05

Court’s reasoning

  1. 01

    Sales of Goods Ordinance (Hong Kong) s.55(1)

    Where there is a breach of warranty buyer is not entitled to reject goods but may claim damages or set off against the price

  2. 02

    Common law (parol evidence rule)

    Parol evidence rule: oral statements contradicting written contract terms are inadmissible to alter the written contract

  3. 03

    Agency law (common law principles)

    An agent must have authority to bind a principal; unauthorised promises by employee do not bind employer

  4. 04

    Contract law principles (acceptance by conduct)

    Acceptance of goods may be inferred from conduct including arranging payment and failing to repudiate

06

Ratio, limits and disposition

Ratio decidendi

The Court found no evidence Ocean rejected the goods; the alleged oral delivery-only-on-request term was either inadmissible as contradicting the written contract or was beyond the agent's authority; the maintenance period issue was a breach of warranty under s.55(1) and did not permit rejection; the signed quotation by Tech-Trans Telecom made it party to the contract; accordingly TT System's claim failed and ELM succeeded on its counterclaim against Tech-Trans Telecom for US$98,641.86 plus interest.

Obiter and limits

  • Machine Chan’s contemporaneous conduct (seeking amendment of maintenance period and arranging payment) indicated intention to accept rather than to reject
  • Internal emails and solicitor release request for deposit supported finding of acceptance by Ocean
  • Even if an oral delivery term had been made, TT Telecom did not ultimately rely on it to reject the goods

Court disposition

Claim by Tech-Trans System Limited dismissed; counterclaim by ELM Computer Technologies Limited allowed against Tech-Trans Telecom Limited.

  • Judgment for ELM Computer Technologies Limited against Tech-Trans Telecom Limited in the sum of US$98,641.86 with interest at judgment rate from 12 April 2005 until satisfaction.
  • Order nisi to be made absolute in 14 days: (1) costs in the original action to be borne by Tech-Trans System Limited, to be taxed if not agreed, with certificate for Counsel; (2) ELM to bear the costs of the counterclaim against Tech-Trans System Limited, to be taxed if not agreed, with certificate for Counsel; (3) Tech-Trans Telecom Limited to pay to ELM the costs of the counterclaim, to be taxed if not agreed, with certificate for Counsel.

Source and reliance status

District Court · 21 August 2007

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

District Court

Judgment· 21 August 2007

TECH-TRANS SYSTEM LTD v. ELM COMPUTER TECHNOLOGIES LTD

bjbj DCCJ1200/2005

IN THE DISTRICT COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO. 1200 OF 2005 ---------------------

BETWEEN Tech-Trans System Limited Plaintiff And ELM Computer Technologies Limited (by original action) Defendant

AND BETWEEN ELM Computer Technologies Limited Plaintiff And Tech-Trans System Limited Tech-TransTelecom Limited (by counter-claim) Defendants -------------------- Coram : H. H. Judge Chow Dates of Hearing : 6th and 8th June, 2007 Date of handing down Judgment : 21st August, 2007

JUDGMENT This is the claim by Tech-Trans System Limited (TT System) against ELM Computer Technologies Limited ( ) for loss of profit in the sum of $70,809.50 in the sub-sale of certain computer software ( the goods ) to Ocean Technology (Asia) Limited ( Ocean ). On the other hand ELM counterclaims against Tech-Trans Telecom Limited (TT Telecom), and alternatively TT System, for the sum of US$98,641.86 for the sale of the goods. On 21 June 2004, a Miss Phoebe Lam of IBM Hong Kong phoned up Mr. Machine Chan of TT System/TT Telecom, saying that she would introduce a client (Ocean) to him. She told him that Ocean had approached them for the purchase of certain products. She had asked Ocean to order the products through TT System, and the products had to be ordered by TT System through ELM. Phoebe Lam emailed to Machine Chan a list of items to be ordered by Ocean, namely, software licences for 7 different IBM software programs. On 25 June 2004 she sent to ELM the same list of the 7 software licences, as well as the details of Ocean. Based on this list, ELM prepared a quotation, in which the name Tech-Trans was used. Upon receiving the quotation, Machine Chan sent a e-mail to Martin Yung of ELM, asking him to include media packs (CD-Rom for the software) and documents packs (user manual for the software) for the 7 software programs in the quotation. Martin Yung prepared a revised

quotation and faxed it to Machine Chan for his signature. Then Machine Chan faxed it back to Martin Yung. On the revised quotation, Machine Chan put down the words System Ltd after the words Tech-Trans . On 25th June, 2004 ELM placed a purchase order with IBM Singapore for all the goods. On 28 June 2004, a further revised quotation for the goods was signed by TT Telecom in place of TT System. By 28 June 2004, IBM delivered the 7 software licences to Ocean directly by e-mail in the form of a document called Proof of Entitlement on which it was expressed that the software maintenance period covered from 26 June 2004 to 30 June 2005. On 23 July 2004, ELM delivered to TT Telecom the media packs and document packs for the 7 software licences, as well as a hard copy of the 7 software licences for their record. TT Telecom rejected the goods and refused to settle ELM s invoice. It is the evidence of Machine Chan that on or about 25 June 2004, Martin Yung contacted him over the phone. During the telephone conversation, they agreed that ELM would supply the goods, and: (a) that delivery for the goods should only be made upon the request of TT System, and (b) ELM should procure software maintenance service of the goods covering a period of 12 months from the date of delivery. During cross-examination, Martin Yung denied that term (a) had been reached but conceded that during the telephone

conversation Machine Chan did request that ELM should not deliver the goods unless requested to do so, and it was agreed that ELM should procure software maintenance service of the goods covering a period of 12 months from the date of delivery. Later on, Martin Yung sent a draft quotation to Machine Chan. When he saw that the delivery date on the quotation was to be approximately 4 - 6 weeks , Machine Chan requested Martin Yung to put down the agreed term on delivery in writing. Martin Yung rejected the request, explaining that it was against the policy of his company to agree to such a term. But eventually Martin Yung agreed that delivery would be made upon Machine Chan s direction. On 23 July 2004, Machine Chan sent a e-mail to Martin Yung, stating, We do not accept the delivery of software on your D.O. DN2004-0182. As we did not issue delivery instruction to your company before. Please collect back asap. Martin Yung said that he called up Machine Chan after receiving this e-mail. This was not mentioned in his two witness statements. The evidence relating to the e-mail sent on 23 July, 2004 is consistent with Machine Chan s evidence that a term on the delivery of the goods had been reached during the conversation between the two of them on or about 25th June, 2004. I accept the evidence of Machine Chan in this respect. However Martin Yung simply did not have the authority to

enter the agreement. So whatever he agreed in this respect cannot be binding upon his employer ELM. Further this verbal agreement is a piece of inadmissible evidence because it contradicts the written term of the contract. Even if such an agreement was binding upon ELM, did TT Telecom rely on such a breach to reject the goods? In its first official reply letter (dated 16th September, 2004) to ELM, TT Telecom no longer complained that the goods were delivered before any request had been made, as indicated in its e-mail dated 23 July, 2004. The letter reads:- Referring to your Quotation (Q2004/06/S0425) dated 25 June 2004. We will not agree to settle your invoice (CT2407043) as what your delivered are not consistent with the goods we ordered. We find that the Quotation was signed and faxed to us on 28 June 2004, therefore the contract was concluded on 28 June 2004. You delivered the products on 23 July 2004 while all the 1 year software licenses maintenance coverage period commenced on 26 June 2004 which are much earlier than the concluded contract date and the delivery date. In this circumstance, please clarify with our Sales Manager Mr. Machine Chan for the dispute and replace the goods with proper maintenance coverage period. The emphasis of this letter is on the insufficiency of the maintenance period.

12. It is clear from paragraph 10 of the witness statement of Machine Chan that his real intention was not to reject the goods, on the ground that no delivery instruction had been given to ELM. Paragraph 10 reads: - 10. Upon receipt of the Products from ELM, I contracted OTAL to ascertain whether they had completely installed their computer system. I was told by OTAL that they had received a copy of the Proof of Entitlement from IBM direct and noted that the software maintenance period had already started on 26th June 2004, i.e. about a month prior to the delivery of the Products to TT System. I was told by OTAL that they would not accept the Products unless the software maintenance period was amended. Thereafter, I contacted Martin Yung by telephone and told him to amend the software maintenance period so that the same would only start to run from the date of delivery. Martin Yung told me that he would see what he could do and would revert to me. I sent Martin Yung an email to protest on the same day, i.e. 23rd July 2004. It is clear from this paragraph that Machine Chan did not really intend to reject the goods as indicated in the e-mail dated 23rd July, 2004, because Ocean had not yet rejected the goods. If he really had had the intention to reject the goods right away he would not have told Martin Yung to amend the software maintenance period. Ocean would accept the goods if the software maintenance period was amended. It is under such circumstances that he sent the e-mail.

13. The IBM s Passport Advantage Express includes a maintenance feature, which includes product upgrades and technical support. It is a benefit collateral to the software license. Therefore the duration of the maintenance period must be a warranty. Section 55(1) of the Sales of Goods Ordinance provides:- (1) Where there is a breach of warranty by the seller, or where the buyer elects, or is compelled, to treat any breach of a condition on the part of the seller as a breach of warranty, the buyer is not, by reason only of such breach of warranty, entitled to reject the goods; but he may- set up against the seller the breach of warranty in diminution or extinction of the price; or (b) maintain an action against the seller for damages for the breach of warranty. Under this section, nether Ocean nor TT Telecom was entitled to reject the goods because of insufficient maintenance period. Did Ocean reject the goods?

14. There is a letter dated 9 November 2004 from Ocean to Lau Kwong & Hung, Solicitors, which reads:- Referring to our contract with supplier (Tech-Trans System Limited) on 25th June 2004, we have agreed with our supplier alternatively instead of the previous payment method. Please release our deposit with HKD420,108.00 held on your stakeholder s account to Tech-Trans System Limited upon you received this letter.

15. Ocean s deposit ($420,108) in relation to the purchase of the goods were stakeheld by a firm of solicitors, Lau Kwong & Hung. The deposit was to be transferred from that law firm solicitors to TT System. If Ocean had rejected the goods, it would be under no duty to make any payment for the goods, and therefore it would not have asked that law firm to release the its deposit to TT System. So it must have accepted the goods, and the deposit to TT System as payment. This is in line with the internal e-mail issued by IBM china/HK Ltd. On 11th November, 2004, which reads: - Please note Tech-trans is working out with Ocean Technology an acceptable payment terms to have this resolved in stead of cancelling the order. Tech-trans has drafted the letter for Ocean Technology s review and signature to release the fund HKD420K held by legal firm for this project. This is about half the full payment. Douglas just talked to Ocean Technology and Ocean Technology agrees to release the above fund to Tech-trans first in stead of canceling the order. Ocean Technology will fax the signed letter today to me first and then I will give that to Machine to ensure and help facilitate the payment. I will keep you posted on this progress and then you can help work out an something between ELM and Tech-trans in stead of canceling the order.

16. TT Systems claims against ELM for loss of profit from the sub-sale of the goods to Ocean because Ocean rejected the goods, and as a result the sub-sale did not go through. But there is no evidence that Ocean rejected the goods. Instead Ocean accepted the goods. Therefore its claim must fail.

17. It is TT Telecom which signed the final version of the quotation of the goods issued by ELM, stating Confirmed and Accepted by Tech-Trans Telecom . Its company chop was stamped next to the signature. The goods were in fact delivered to TT Telecom. Hence it is TT Telecom which assumed the rights and obligations of TT System under the agreement. Therefore the proper plaintiff in the original action is TT Telecom and not TT System.

18. For these reasons I dismiss the claim of the Plaintiff (TT System) in the original action.

19. As for ELM s counterclaim for the full price of the goods, there is no claim in the pleading of TT System or TT Telecom and no evidence has been adduced to show that there is a diminution in the value of the software licences because of insufficient maintenance period. Therefore this court will not make any reduction in this regard.

20. I enter judgment in favour of the Plaintiff (ELM) in the counterclaim against Tech-Trans Telecom Limited in the sum of US$98,641.86, with interests thereon at judgment rate, commencing from 12th April, 2005, until satisfaction. Costs 21. I make an order nisi, to be made absolute in 14 days time, that (1) the costs in the original action be borne by Tech-Trans System Limited, to be taxed, if not agreed, with certificate for Counsel; (2) ELM Computer Technologies Limited is to bear the costs of the counterclaim against Tech-Trans System Limited, to be taxed, if not agreed, with certificate for Counsel; (3) Tech-Trans Telecom Limited is to pay to ELM Computer Technologies Limited costs of the counterclaim, to be taxed, if not agreed, with certificate for Counsel. ( S. Chow ) District Judge The Plaintiff by original action and the Defendants by counterclaim: represented by Mr. Jenkin Suen, instructed by Messrs. Cheung & Yip, Solicitors. The Defendant by original action and the Plaintiff by counterclaim: represented by Mr. Jonathan Chang, instructed by Messrs. A.M. Mui & Kwan, Solicitors.

PAGE -

PAGE

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R S T 1udk 1udk

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T U V (#p# &`#$ :i#z *\mT zo/< xC&1 ({m8 fX-Jz P0} W~7gb W~7g xC&1 ({m8 fX-J & 6" ABC.dot setup Microsoft Word 9.0 Judiciary Title Microsoft Word Document MSWordDoc Word.Document.8

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Sales of Goods Ordinance s.55(1)

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.