CHUNG FAI ENGINEERING CO. (a firm) v. MAXWELL ENGINEERING CO. LTD.
The court found there was no back-to-back/pay-when-paid term, the 18 July 1996 supplementary agreement was valid and not procured by economic duress, the $2.05m cheque was not conditional, and the termination on 12 August 1996 was wrongful because material delays were caused by lack of power/water and supplier delays; accordingly Maxwell was entitled to judgment on its counterclaim for unpaid work in the sum of $6,071,000 plus interest and costs.
- Citation
- CHUNG FAI ENGINEERING CO. (a firm) v. MAXWELL ENGINEERING CO. LTD.
- Parties
- Plaintiff (hca10504) / Defendant (hca10631): Chung Fai Engineering Co. (a firm); Defendant (hca10504) / Plaintiff (hca10631): Maxwell Engineering Co. Ltd.
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 27 June 2000
- Case Number
- HCA10631/1996
- Procedural Posture
- Construction Contract Dispute Breach of Contract and Payment / Judgment (trial)
- Outcome
- Plaintiff's (Chung Fai) claim dismissed; judgment for defendant (Maxwell) on counterclaim.
- Legal Topics
- Termination, Payment Disputes, Economic Duress, Dishonoured Cheque, Quantum of Damages
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Chung Fai Engineering Co. (a firm)
Plaintiff (hca10504) / Defendant (hca10631)
Maxwell Engineering Co. Ltd.
Defendant (hca10504) / Plaintiff (hca10631)
Procedural Posture
Construction Contract Dispute Breach of Contract and Payment / Judgment (trial)
Legal Issues
- 1 Whether the original subcontract included an oral 'pay when paid' (back-to-back) clause
- 2 Whether the 18 July 1996 supplementary agreement was valid or procured by economic duress
- 3 Whether the $2.05 million cheque was conditional on completion of works for the Fire Services inspection
Ratio Decidendi
The court found there was no back-to-back/pay-when-paid term, the 18 July 1996 supplementary agreement was valid and not procured by economic duress, the $2.05m cheque was not conditional, and the termination on 12 August 1996 was wrongful because material delays were caused by lack of power/water and supplier delays; accordingly Maxwell was entitled to judgment on its counterclaim for unpaid work in the sum of $6,071,000 plus interest and costs.
Court Disposition
Plaintiff's (Chung Fai) claim dismissed; judgment for defendant (Maxwell) on counterclaim.
Orders
- Plaintiff's claim dismissed with costs
- Judgment for defendant on counterclaim in the sum of 6,071,000 HKD
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment