YING KWONG CONSTRUCTTON CO v. ATTORNEY GENERAL

YING KWONG CONSTRUCTTON CO v. ATTORNEY GENERAL

Government, by its conduct and by permitting the court order for extension of time (Silke J) and by participating in the appointment of an arbitrator, was estopped and had waived the right to contend that the dispute was excluded from Clause 117 as an 'excepted matter' under Clause 115; the Architect had not decided...

Source-derived case information.

Citation
YING KWONG CONSTRUCTTON CO v. ATTORNEY GENERAL
Parties
Claimant: Ying Kwong Construction Company; Respondent: The Attorney General
Court
Court of First Instance
Jurisdiction
Hong Kong
Judgment Date
13 June 1981
Case Number
HCMP510/1981
Procedural Posture
Public Works Department Building Contract Dispute; Arbitration Referral Under Arbitration Ordinance / Special Case Stated Under Arbitration Ordinance S.23; Judgment on Special Case (application Under S.29 for Extension of Time)
Outcome
Special case answered: matters in claim are at least initially 'excepted matters' for the Architect; Architect has not given a Clause 115 decision; Government has waived/estopped reliance on Clause 115 and cannot deny arbitration under Clause 117; claimant not entitled to a conclusive court determination on Clause 6...
Legal Topics
Arbitration Clause, Excepted Matters (architect's Determinations), Estoppel by Conduct and by Record, Waiver, Interpretation of Bills of Quantities, Jurisdiction of Arbitrator, Extension of Time Under S.29 Arbitration Ordinance
Source Language
en
Contract Law Arbitration Law Construction Law Estoppel/res Judicata Public Law Arbitration Clause Excepted Matters (architect's Determinations) Estoppel by Conduct and by Record +4 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Ying Kwong Construction Company

Claimant

The Attorney General

Respondent

Procedural Posture

Public Works Department Building Contract Dispute; Arbitration Referral Under Arbitration Ordinance / Special Case Stated Under Arbitration Ordinance S.23; Judgment on Special Case (application Under S.29 for Extension of Time)

  1. 1 Whether matters pleaded are 'excepted matters' under Clause 115
  2. 2 Whether the Architect gave a decision under Clause 115
  3. 3 Whether claimants entitled to payment under Clause 6 for rock excavation

Ratio Decidendi

Government, by its conduct and by permitting the court order for extension of time (Silke J) and by participating in the appointment of an arbitrator, was estopped and had waived the right to contend that the dispute was excluded from Clause 117 as an 'excepted matter' under Clause 115; the Architect had not decided the Clause 115 issues and a decision deliberately made under Clause 117 cannot be treated as if made under Clause 115, but Government cannot retract the position it implicitly adopted before the court and arbitrator.

Court Disposition

Special case answered: matters in claim are at least initially 'excepted matters' for the Architect; Architect has not given a Clause 115 decision; Government has waived/estopped reliance on Clause 115 and cannot deny arbitration under Clause 117; claimant not entitled to a conclusive court determination on Clause 6...

Orders

  • Special case dealt with in terms of judgment.
  • Questions disposed of accordingly.