The Incorporated Owners of Tak Cheong Building (Battery Street) v. Tong Wai Tak

The Incorporated Owners of Tak Cheong Building (Battery Street) v. Tong Wai Tak

The Tribunal found the Deed of Mutual Covenant and the owners' EGM authorised the lift renovation, the tendering process (invitations to six firms, three tenders received) was not unlawful, accounts were available for inspection and the respondent produced no evidence that the fee was excessive; therefore respondent...

Source-derived case information.

Citation
The Incorporated Owners of Tak Cheong Building (Battery Street) v. Tong Wai Tak
Parties
Applicant: The Incorporated Owners of Tak Cheong Building (Battery Street); Respondent: Tong Wai Tak
Court
Lands Tribunal
Jurisdiction
Hong Kong
Judgment Date
8 February 2000
Case Number
LDBM41/1999
Procedural Posture
Building Management Application Ldbm41/1999 / Final Judgment
Outcome
Judgment for the Applicant against the Respondent
Legal Topics
Management Fee Recovery, Deed of Mutual Covenant, Tendering Procedures, Building Management Ordinance S44, Lift Renovation Contributions
Source Language
et
Building Management Property Law Contract Civil Procedure Administrative Compliance Management Fee Recovery Deed of Mutual Covenant Tendering Procedures +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 1 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

The Incorporated Owners of Tak Cheong Building (Battery Street)

Applicant

Tong Wai Tak

Respondent

Procedural Posture

Building Management Application Ldbm41/1999 / Final Judgment

  1. 1 Whether respondent liable for arrears of management fees
  2. 2 Whether respondent liable for contribution to lift renovation
  3. 3 Whether tendering procedure breached statutory Code of Practice making charges illegal

Ratio Decidendi

The Tribunal found the Deed of Mutual Covenant and the owners' EGM authorised the lift renovation, the tendering process (invitations to six firms, three tenders received) was not unlawful, accounts were available for inspection and the respondent produced no evidence that the fee was excessive; therefore respondent was liable for arrears, lift contribution and interest and costs.

Court Disposition

Judgment for the Applicant against the Respondent

Orders

  • Judgment entered for the Applicant against the Respondent in the sum of $17,945.29.
  • Arrears of management fee to be paid at the rate of $600.00 per calendar month from 1 March 1999 to the date of judgment.