WAH SUNG CONSTRUCTION & PILING LTD v. CHEERWIDE LTD

WAH SUNG CONSTRUCTION & PILING LTD v. CHEERWIDE LTD

The Varied Contractor Agreement produced by Wah Sung/Alliance (including the Excepted List and Initial Approved Plans) was the true contract; it was not void for uncertainty. Many Additional Works were outside the VCA and authorised by Alliance and/or ratified or acquiesced in by Cheerwide (actual and ostensible authority), so Wah Sung was entitled to payment for agreed additional works (HK$34,300,469.25) and quantum meruit items (HK$730,533.70) together with levies, administrative fee, HD payments and delay losses. Cheerwide’s counterclaims against Wah Sung, Alliance and Chiu failed; Chiu owed no personal tortious duty. The judge applied objective contractual construction principles, the...

Citation
[2024] HKCFI 45
Parties
Plaintiff (by Original Action); 1st Defendant (by Counterclaim): Wah Sung Construction & Piling Limited; Defendant (by Original Action); Plaintiff (by Counterclaim): Cheerwide Limited; 2nd Defendant (by Counterclaim): Alliance Architects Limited; 3rd Defendant (by Counterclaim): Chiu Sung Kin
Court
Court of First Instance
Jurisdiction
Hong Kong
Judgment Date
10 January 2024
Case Number
HCCT57/2020
Procedural Posture
Construction and Arbitration Proceedings / Trial (judgment Delivered 10 January 2024)
Outcome
Judgment entered for Wah Sung; Cheerwide’s counterclaims against Wah Sung, Alliance and Chiu dismissed; final sum awarded to Wah Sung HKD22,974,308.29; Chiu not liable personally.
Legal Topics
Variation Orders, Lump Sum Contract Construction, Time at Large/prevention Principle, Assumption of Responsibility, Final Account and Certification, Liquidated Damages, Retention Money, Costs and Interest
Source Language
EN

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 6 Authorities cited 13 Party arguments 2 Amounts and remedies 9
Sign in to unlock

Parties

Wah Sung Construction & Piling Limited

Plaintiff (by Original Action); 1st Defendant (by Counterclaim)

Cheerwide Limited

Defendant (by Original Action); Plaintiff (by Counterclaim)

Alliance Architects Limited

2nd Defendant (by Counterclaim)

Chiu Sung Kin

3rd Defendant (by Counterclaim)

Procedural Posture

Construction and Arbitration Proceedings / Trial (judgment Delivered 10 January 2024)

  1. 1 Entitlement to 95% of the Contract Sum
  2. 2 Which version of the Varied Contractor Agreement is the true contract
  3. 3 Whether the contract is void for uncertainty

Ratio Decidendi

The Varied Contractor Agreement produced by Wah Sung/Alliance (including the Excepted List and Initial Approved Plans) was the true contract; it was not void for uncertainty. Many Additional Works were outside the VCA and authorised by Alliance and/or ratified or acquiesced in by Cheerwide (actual and ostensible authority), so Wah Sung was entitled to payment for agreed additional works (HK$34,300,469.25) and quantum meruit items (HK$730,533.70) together with levies, administrative fee, HD payments and delay losses. Cheerwide’s counterclaims against Wah Sung, Alliance and Chiu failed; Chiu owed no personal tortious duty. The judge applied objective contractual construction principles, the...

Court Disposition

Judgment entered for Wah Sung; Cheerwide’s counterclaims against Wah Sung, Alliance and Chiu dismissed; final sum awarded to Wah Sung HKD22,974,308.29; Chiu not liable personally.

Orders

  • Judgment in favour of Wah Sung Construction & Piling Limited against Cheerwide Limited in the sum of HKD22,974,308.29.
  • Interest order nisi: interest on HKD22,974,308.29 at prime plus one from writ date 14 September 2020 to judgment date and at judgment rate thereafter until payment.