YING HO CO LTD AND OTHERS v. THE SECRETARY FOR JUSTICE

YING HO CO LTD AND OTHERS v. THE SECRETARY FOR JUSTICE

The Court held the Director had power under the DDH clause to withhold approval on aviation‑safety height grounds provided no derogation from the grant resulted; the only implied contractual term was that the building covenant period would be extended if the Government culpably delayed or unduly delayed processing...

Source-derived case information.

Citation
YING HO CO LTD AND OTHERS v. THE SECRETARY FOR JUSTICE
Parties
Appellant: Ying Ho Company Limited; Appellant: Kwong Fook Investors & Developers Ltd; Appellant: Cheong Ming Investment Co. Ltd; Appellant: The World Realty Limited; Appellant: Yau Fook Hong Co. Ltd; Appellant: Tsing Lung Investments Co. Ltd; Appellant: Dorfolk Investments Ltd; Appellant: On Lee Investment Co. Ltd; Respondent: The Secretary for Justice
Court
Court of Final Appeal
Jurisdiction
Hong Kong
Judgment Date
23 September 2004
Case Number
FACV17/2003
Procedural Posture
Civil Appeal (final) / Final Appeal Judgment
Outcome
Appeal dismissed
Legal Topics
Lease Conditions, DDH Clause (design Disposition and Height), Building Covenant, Liquidated Damages, Re Entry/forfeiture, Implied Terms, Instrument Landing System (ils), Airport Obstruction Controls, Payments Under Protest, Estoppel, Penalty Doctrine
Source Language
et
Administrative Law Contract Law Property Law Aviation Law Restitution / Equity Lease Conditions DDH Clause (design Disposition and Height) Building Covenant +8 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 15 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Ying Ho Company Limited

Appellant

Kwong Fook Investors & Developers Ltd

Appellant

Cheong Ming Investment Co. Ltd

Appellant

The World Realty Limited

Appellant

Yau Fook Hong Co. Ltd

Appellant

Tsing Lung Investments Co. Ltd

Appellant

Dorfolk Investments Ltd

Appellant

On Lee Investment Co. Ltd

Appellant

The Secretary for Justice

Respondent

Procedural Posture

Civil Appeal (final) / Final Appeal Judgment

  1. 1 Whether Government could withhold MLP approval under DDH clause on ground that proposed height exceeded a height it expected to fix under Cap.301
  2. 2 What duties Government owed in processing MLPs (speed, reasons/criteria disclosure)
  3. 3 Whether Government caused substantial delay up to April 1996 (by rejecting MLPs for prospective height limit, taking too long to decide height controls, or taking too long to reject an excessive MLP)

Ratio Decidendi

The Court held the Director had power under the DDH clause to withhold approval on aviation‑safety height grounds provided no derogation from the grant resulted; the only implied contractual term was that the building covenant period would be extended if the Government culpably delayed or unduly delayed processing so as to prevent completion; on the facts the courts below correctly found Government did not cause such delay up to April 1996; accordingly Government was entitled to retain its remedies and the appeal is dismissed, with the issue of reimbursement of amounts paid under protest left open for further trial where relevant.

Court Disposition

Appeal dismissed

Orders

  • Appeal dismissed
  • Order nisi that Appellants pay Respondent's costs, certified fit for three counsel; parties to file written representations on costs within 21 days with any replies within a further 21 days