RAKESH KUMAR JAIN AND ANR. versus STATEOF U.P. THR. COLLECTOR AND ANR.
Appellants were wrongly deprived of the beneficial use of their money due to delayed payment of compensation; they are entitled to simple interest at the rate of 18% per annum from the date of possession of the land till the date of actual payment.
- Parties
- Appellants: Rakesh Kumar Jain and Anr.; Respondents: State of U.P. thr. Collector and Anr.
- Jurisdiction
- India
- Judgment Date
- 05 January 2007
- Procedural Posture
- Civil Appeal / Final Judgment, Appeal Disposed
- Outcome
- Appeal disposed of; High Court order set aside
- Legal Topics
- Acquisition of Land, Compensation, Interest on Delayed Payment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Rakesh Kumar Jain and Anr.
Appellants
State of U.P. thr. Collector and Anr.
Respondents
Procedural Posture
Civil Appeal / Final Judgment, Appeal Disposed
Legal Issues
- 1 Whether land owners are entitled to interest on delayed payment of compensation after forcible possession of land was taken without resort to Land Acquisition Act
Ratio Decidendi
Appellants were wrongly deprived of the beneficial use of their money due to delayed payment of compensation; they are entitled to simple interest at the rate of 18% per annum from the date of possession of the land till the date of actual payment.
Court Disposition
Appeal disposed of; High Court order set aside
Orders
- Agra Development Authority to pay simple interest at 18% p.a. on Rs.17,84,974.50 from 31.08.2000 till actual payment.
- Appellants are at liberty to withdraw Rs.17,84,974.50 deposited in civil court without furnishing security.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment