Since the petitioners had not completed the required works as stipulated in the tender conditions by the date of application, the pre-condition was not satisfied and the refusal of the tender forms was justified.

Source-derived case information.

Parties
Petitioner: MIS. SHAPERS CONSTRUCTION (P) LTD.; Respondent: AIRPORT AUTHORITY OF INDIA; Petitioner: ANR.; Respondent: ANR.
Jurisdiction
India
Judgment Date
17 September 1996
Procedural Posture
Special Leave Petition (civil) / Final Order on Petition
Outcome
Petitions dismissed
Legal Topics
Tender Conditions, Eligibility for Tender, Completion of Works, Writ Petition
Administrative Law Tender Conditions Eligibility for Tender Completion of Works Writ Petition

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

MIS. SHAPERS CONSTRUCTION (P) LTD.

Petitioner

AIRPORT AUTHORITY OF INDIA

Respondent

ANR.

Petitioner

ANR.

Respondent

Procedural Posture

Special Leave Petition (civil) / Final Order on Petition

  1. 1 Whether the petitioners satisfied the pre-condition of completing required works to be eligible for tender.
  2. 2 Whether refusal to issue tender forms violated petitioners' rights.

Ratio Decidendi

Since the petitioners had not completed the required works as stipulated in the tender conditions by the date of application, the pre-condition was not satisfied and the refusal of the tender forms was justified.

Court Disposition

Petitions dismissed

Orders

  • Petitions dismissed