ASSAM STATE ELECTRICITY BOARD AND ORS. versus BUILDWORTH PVT. LTD.

ASSAM STATE ELECTRICITY BOARD AND ORS. versus BUILDWORTH PVT. LTD.

Where a contractor works beyond the formal extension of time without objection, contractual ceilings on escalation do not apply, and the arbitrator may properly award escalation for the extended period. The arbitrator’s findings on contributory delay and idling charges, having considered relevant factors, do not...

Source-derived case information.

Parties
Appellant: Assam State Electricity Board and Ors.; Respondent: Buildworth Pvt. Ltd.
Jurisdiction
India
Judgment Date
04 July 2017
Procedural Posture
Civil Appeal / Supreme Court Appellate Decision
Outcome
Appeal filed by claimant allowed; appeal by Board dismissed
Legal Topics
Arbitration Award, Price Escalation in Contracts, Interest on Arbitral Award, Idling Charges, Construction Contracts
Arbitration Contract Law Arbitration Award Price Escalation in Contracts Interest on Arbitral Award Idling Charges Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 2 Authorities cited 12 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Assam State Electricity Board and Ors.

Appellant

Buildworth Pvt. Ltd.

Respondent

Procedural Posture

Civil Appeal / Supreme Court Appellate Decision

  1. 1 Entitlement to price escalation beyond contractual ceiling in extended contract period
  2. 2 Entitlement to idling charges when there is contributory delay by claimant
  3. 3 Arbitrator's power to award interest prior to date of decree under Arbitration Act, 1940 and Interest Act, 1978

Ratio Decidendi

Where a contractor works beyond the formal extension of time without objection, contractual ceilings on escalation do not apply, and the arbitrator may properly award escalation for the extended period. The arbitrator’s findings on contributory delay and idling charges, having considered relevant factors, do not warrant interference. The arbitrator, under Section 3(1)(b) of the Interest Act, 1978, may award interest from the date of written notice, even for pre-reference periods, absent contractual prohibition.

Court Disposition

Appeal filed by claimant allowed; appeal by Board dismissed

Orders

  • Claimant entitled to interest on awarded sum from 20 April 1987 to 31 December 1997 and thereafter from date of decree until payment or realisation at 12% per annum for both periods.