M/S. B.P.L. LTD. AND ORS. versus R. SUDHAKAR AND ORS.

M/S. B.P.L. LTD. AND ORS. versus R. SUDHAKAR AND ORS.

A dispute is not pending before the Tribunal for purposes of Section 33(2)(b) of the Industrial Disputes Act, 1947 if the operation of the order of reference is stayed by court; complaint under Section 33A is not maintainable when no proceedings are pending due to such stay.

Parties
Appellant: B.P.L. Ltd. and Others; Respondent: R. Sudhakar and Others
Jurisdiction
India
Judgment Date
06 May 2004
Procedural Posture
Civil Appeal / Final Supreme Court Decision
Outcome
Appeals allowed; preliminary objection upheld; complaint dismissed as not maintainable.
Legal Topics
Industrial Disputes Act, Stay of Reference, Maintainability of Complaint, Section 33(2)(b), Section 33 a

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Legal principles 4 Authorities cited 11 Party arguments 2
Sign in to unlock

Parties

B.P.L. Ltd. and Others

Appellant

R. Sudhakar and Others

Respondent

Procedural Posture

Civil Appeal / Final Supreme Court Decision

  1. 1 Whether a dispute is pending before an Industrial Tribunal for the purpose of proviso to Section 33(2)(b) of the Industrial Disputes Act, 1947 during the period when operation of order of reference itself remained stayed

Ratio Decidendi

A dispute is not pending before the Tribunal for purposes of Section 33(2)(b) of the Industrial Disputes Act, 1947 if the operation of the order of reference is stayed by court; complaint under Section 33A is not maintainable when no proceedings are pending due to such stay.

Court Disposition

Appeals allowed; preliminary objection upheld; complaint dismissed as not maintainable.

Orders

  • The preliminary objection raised by appellant companies is upheld.
  • The complaint by respondent-workmen under Section 33A is dismissed as not maintainable.