BIJLI COTTON MILL (UNIT OF NATIONAL TEXTILE CORPORATION U.P. LIMITED) versus U.P. POWER CORPORATION LIMITED & ORS.

BIJLI COTTON MILL (UNIT OF NATIONAL TEXTILE CORPORATION U.P. LIMITED) versus U.P. POWER CORPORATION LIMITED & ORS.

Matter relating to whether late payment surcharge is covered by the BIFR waiver of interest and damages must be clarified by BIFR; High Court erred in not considering the effect of the scheme and related correspondence, and not differentiating Lord Krishna Mills case.

Source-derived case information.

Parties
Appellant: BULi Cotton Mill (Unit of National Textile Corporation U.P. Limited); Respondent: U.P. Power Corporation Limited & Ors.
Jurisdiction
India
Procedural Posture
Civil Appeal / Appeal From Allahabad High Court Judgment in Civil Misc. Writ Petition No. 56241 of 2005
Outcome
Appeal allowed to the extent of remitting matter to High Court for reconsideration after BIFR clarification.
Legal Topics
Sick Industrial Companies (special Provisions) Act, Electricity Payment—interest and Damages, Late Payment Surcharge, Binding Scheme From BIFR
Company Law Electricity Law Sick Industrial Companies (special Provisions) Act Electricity Payment—interest and Damages Late Payment Surcharge Binding Scheme From BIFR

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

BULi Cotton Mill (Unit of National Textile Corporation U.P. Limited)

Appellant

U.P. Power Corporation Limited & Ors.

Respondent

Procedural Posture

Civil Appeal / Appeal From Allahabad High Court Judgment in Civil Misc. Writ Petition No. 56241 of 2005

  1. 1 Whether late payment surcharge is included in 'interest and damages' to be waived under BIFR approved scheme clauses 5.03(v) and 5.04.
  2. 2 Whether the demand for late payment surcharge by U.P. Power Corporation is contrary to the scheme approved by BIFR.

Ratio Decidendi

Matter relating to whether late payment surcharge is covered by the BIFR waiver of interest and damages must be clarified by BIFR; High Court erred in not considering the effect of the scheme and related correspondence, and not differentiating Lord Krishna Mills case.

Court Disposition

Appeal allowed to the extent of remitting matter to High Court for reconsideration after BIFR clarification.

Orders

  • Parties to move BIFR for clarification on whether late payment surcharge is included in interest or damages.
  • Order of BIFR to be placed before High Court.