G H CENTURY RAYON LIMITED versus IVP LIMITED AND OTHERS
The injunction order restraining the appellant and the electricity company lacked justification because necessary permissions were obtained, compensation remedy is available, 80% of the work was complete, and the balance of convenience and public interest do not support continuing interim relief.
- Parties
- Appellant: Century Rayon Limited; First Respondent: IVP Limited; Second Respondent: Maharashtra State Electricity Distribution Company Limited (MSEDC)
- Jurisdiction
- India
- Judgment Date
- 27 November 2019
- Procedural Posture
- Civil Appeal / Final Decision on Appeal Against High Court Interim Order
- Outcome
- Appeal allowed, impugned order and injunction order set aside
- Legal Topics
- Interim Injunction, Balance of Convenience, Transmission of Electricity, Land Use for Public Utilities, Compensation Under Telegraph Act
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Century Rayon Limited
Appellant
IVP Limited
First Respondent
Maharashtra State Electricity Distribution Company Limited (MSEDC)
Second Respondent
Procedural Posture
Civil Appeal / Final Decision on Appeal Against High Court Interim Order
Legal Issues
- 1 Whether interim injunction restraining electricity transmission works on respondent's land should be continued
- 2 Whether balance of convenience justifies interim relief
- 3 Legal requirements for permission and compensation under Telegraph Act for use of third party land
Ratio Decidendi
The injunction order restraining the appellant and the electricity company lacked justification because necessary permissions were obtained, compensation remedy is available, 80% of the work was complete, and the balance of convenience and public interest do not support continuing interim relief.
Court Disposition
Appeal allowed, impugned order and injunction order set aside
Orders
- Impugned High Court order and injunction order set aside
- Appellant to make ad hoc payment of Rs. 20,00,000/- to first respondent
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment