CHAMUNDESHWARI ELECTRICITY SUPPLY COMPANY LTD. (CESC) versus SAISUDHIR ENERGY (CHITRADURGA) PVT. LTD. & ANR.
Because the Developer did not obtain an extension under Article 5.7 nor issue the notice required by Article 14.5, the preconditions for invocation of Article 4.4 were satisfied and CESC validly encashed the performance security; the State Commission and APTEL erred in treating the delay as Force Majeure and directing restoration, extension and renegotiation contrary to the express contractual scheme.
- Parties
- Appellant: Chamundeshwari Electricity Supply Company Limited; Respondent No.1 (developer): M/s Saisudhir Energy (Chitradurga) Pvt. Ltd.; Respondent No.2 (kptcl): Karnataka Power Transmission Corporation Limited
- Jurisdiction
- India
- Judgment Date
- 25 August 2025
- Procedural Posture
- Civil Appeal No. 6888 of 2018 / Final Judgment of the Supreme Court (appeal Against APTEL Judgment Dated 21.03.2018)
- Outcome
- Appeal allowed; impugned APTEL judgment dated 21.03.2018 and State Commission order dated 28.01.2015 set aside
- Legal Topics
- Performance Bank Guarantee, Force Majeure, Power Purchase Agreement, Conditions Precedent, Contractual Timelines, Tariff Renegotiation, Competence of Regulatory Fora
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Chamundeshwari Electricity Supply Company Limited
Appellant
M/s Saisudhir Energy (Chitradurga) Pvt. Ltd.
Respondent No.1 (developer)
Karnataka Power Transmission Corporation Limited
Respondent No.2 (kptcl)
Procedural Posture
Civil Appeal No. 6888 of 2018 / Final Judgment of the Supreme Court (appeal Against APTEL Judgment Dated 21.03.2018)
Legal Issues
- 1 Effect of KPTCL delay in commissioning 220 kV evacuation system on CPs and COD timelines under the PPA
- 2 Entitlement of CESC to invoke and encash the performance bank guarantee
- 3 Sustainability of Force Majeure finding absent contractual notice under Article 14.5 of the PPA
Ratio Decidendi
Because the Developer did not obtain an extension under Article 5.7 nor issue the notice required by Article 14.5, the preconditions for invocation of Article 4.4 were satisfied and CESC validly encashed the performance security; the State Commission and APTEL erred in treating the delay as Force Majeure and directing restoration, extension and renegotiation contrary to the express contractual scheme.
Court Disposition
Appeal allowed; impugned APTEL judgment dated 21.03.2018 and State Commission order dated 28.01.2015 set aside
Orders
- Impugned judgment of the APTEL dated 21.03.2018 in Appeal No.176 of 2015 set aside
- Order dated 28.01.2015 of the Karnataka State Commission in O.P. No.24 of 2014 set aside
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment