CLP INDIA PVT. LTD. versus GUJARAT URJA VIKAS NIGAM LTD. & ANR.

CLP INDIA PVT. LTD. versus GUJARAT URJA VIKAS NIGAM LTD. & ANR.

The Court held that the amendment notification dated 06.11.1995 issued under Section 43A was statutory and binding and therefore precluded payment of deemed generation incentive; the concurrent findings of GERC and APTEL limiting recovery to three years prior to Gujarat Urja’s application were reasonable and...

Source-derived case information.

Parties
Appellant: CLP India Pvt. Ltd.; Respondent: Gujarat Urja Vikas Nigam Ltd.
Jurisdiction
India
Judgment Date
06 May 2020
Procedural Posture
Civil Appeal Under Section 125, Electricity Act, 2003 / Final Judgment (appeal Dismissed)
Outcome
Appeals dismissed
Legal Topics
Tariff, Power Purchase Agreement, Statutory Notifications Under S.43 a, Deemed Generation Incentive, Change of Law Clause, Debt Equity Ratio, Interest on Deemed Equity, Recovery of Excess Payments, Limitation
Electricity Law Contract Law Regulatory Law Limitation Law Tariff Power Purchase Agreement Statutory Notifications Under S.43 a Deemed Generation Incentive +5 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 19 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

CLP India Pvt. Ltd.

Appellant

Gujarat Urja Vikas Nigam Ltd.

Respondent

Procedural Posture

Civil Appeal Under Section 125, Electricity Act, 2003 / Final Judgment (appeal Dismissed)

  1. 1 Whether the amendment notification dated 06.11.1995 issued under Section 43A of the Electricity (Supply) Act, 1948 applied to the PPA and precluded payment of deemed generation incentive
  2. 2 Whether Gujarat Urja’s claim for recovery of incentive payments was time-barred and if limitation limited recovery to three years prior to filing
  3. 3 Whether interest was payable on the deemed equity amount of Rs.53.90 crores for periods prior to 01.07.2003 or only for the period specified in the supplementary agreement

Ratio Decidendi

The Court held that the amendment notification dated 06.11.1995 issued under Section 43A was statutory and binding and therefore precluded payment of deemed generation incentive; the concurrent findings of GERC and APTEL limiting recovery to three years prior to Gujarat Urja’s application were reasonable and correct; and the supplementary agreement fixed interest on the deemed equity of Rs.53.90 crores only for the period 01.07.2003 to 31.12.2009, precluding claims for interest prior to 01.07.2003. Accordingly the appeals were dismissed.

Court Disposition

Appeals dismissed

Orders

  • Both appeals dismissed
  • No order as to costs