DELHI DEVELOPMENT AUTHORITY versus BATTI & ORS
The High Court erred in holding the acquisition had lapsed; applying the Constitution Bench decision in Indore Development Authority, possession had been taken and therefore Section 24(2) does not operate to lapse the acquisition despite non-payment of compensation; accordingly the appeals are allowed and the writ petition is dismissed.
- Parties
- Appellant: Delhi Development Authority; Appellant: Government of NCT of Delhi; Respondent: Batti & Ors.
- Jurisdiction
- India
- Judgment Date
- 22 March 2023
- Procedural Posture
- Civil Appeal / On Appeal From Order Dated 30.11.2017 of the High Court of Delhi in WPC No.12135/2015
- Outcome
- Appeals allowed
- Legal Topics
- Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Lapse of Acquisition, Possession Versus Payment, Precedent Overruled (pune Municipal Corporation Overruled by Indore Development Authority)
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Delhi Development Authority
Appellant
Government of NCT of Delhi
Appellant
Batti & Ors.
Respondent
Procedural Posture
Civil Appeal / On Appeal From Order Dated 30.11.2017 of the High Court of Delhi in WPC No.12135/2015
Legal Issues
- 1 Whether acquisition lapsed under Section 24(2) of the 2013 Act when compensation was not paid but possession had been taken
- 2 Whether the High Court correctly applied Pune Municipal Corporation & Anr. v. Harakchand Misrimal Solanki & Ors. given subsequent Constitution Bench decision in Indore Development Authority v. Manoharlal & Ors.
- 3 Whether the conditions for deemed lapse under Section 24(2) as interpreted in Indore Development Authority are satisfied
Ratio Decidendi
The High Court erred in holding the acquisition had lapsed; applying the Constitution Bench decision in Indore Development Authority, possession had been taken and therefore Section 24(2) does not operate to lapse the acquisition despite non-payment of compensation; accordingly the appeals are allowed and the writ petition is dismissed.
Court Disposition
Appeals allowed
Orders
- Impugned order of the High Court dated 30.11.2017 is set aside
- Writ petition filed by the respondents in the High Court is dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment