B.B. PATEL & ORS versus DLF UNIVERSAL LTD
The Supreme Court upheld the MRTP Commission's finding that appellants failed to establish misrepresentation or other ingredients of unfair trade practice under the MRTP Act: the ABA permitted reasonable extension of time and contained mechanisms (clause 18) for termination which appellants did not invoke; extra charges were chargeable under express clauses of the ABA and were disclosed; consequently appellants were not entitled to compensation under s.12-B MRTP Act. Nevertheless, in the interest of justice the Court directed respondent to hand over possession of each flat on payment of Rs.25,00,000 per flat by the appellants.
- Parties
- Appellants: B.B. Patel & Ors.; Respondent: DLF Universal Ltd.
- Jurisdiction
- India
- Judgment Date
- 25 January 2022
- Procedural Posture
- Civil Appeal / Appeal Against Judgment of Monopolies and Restrictive Trade Practices Commission Dated 19.01.2009; Disposed by Supreme Court
- Outcome
- Appeal disposed of; MRTP Commission judgment dismissing complaint upheld; Court directed respondent to hand over possession of flats on payment by appellants
- Legal Topics
- Unfair Trade Practice, Misrepresentation, Compensation, Time as Essence of Contract, Unconscionable Contract, Equitable Relief
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
B.B. Patel & Ors.
Appellants
DLF Universal Ltd.
Respondent
Procedural Posture
Civil Appeal / Appeal Against Judgment of Monopolies and Restrictive Trade Practices Commission Dated 19.01.2009; Disposed by Supreme Court
Legal Issues
- 1 Whether delay in handing over possession and demand for extra charges constituted an unfair trade practice under MRTP Act
- 2 Whether the Apartment Buyer Agreement was unconscionable and/or time was made the essence of the contract
- 3 Whether appellants were entitled to compensation under Section 12-B MRTP Act
Ratio Decidendi
The Supreme Court upheld the MRTP Commission's finding that appellants failed to establish misrepresentation or other ingredients of unfair trade practice under the MRTP Act: the ABA permitted reasonable extension of time and contained mechanisms (clause 18) for termination which appellants did not invoke; extra charges were chargeable under express clauses of the ABA and were disclosed; consequently appellants were not entitled to compensation under s.12-B MRTP Act. Nevertheless, in the interest of justice the Court directed respondent to hand over possession of each flat on payment of Rs.25,00,000 per flat by the appellants.
Court Disposition
Appeal disposed of; MRTP Commission judgment dismissing complaint upheld; Court directed respondent to hand over possession of flats on payment by appellants
Orders
- Appeal disposed of
- Order of Monopolies and Restrictive Trade Practices Commission dated 19.01.2009 dismissing complaint upheld
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment