K. SASIDHARAN versus KERALA STATE FILM DEVELOPMENT CORPORATION
Since the arbitration clause was expressly excluded from the contract, clause 73 of MDSS does not apply and there is no arbitrable agreement between the parties. The Civil Court cannot appoint an arbitrator under Section 20 of the Arbitration Act, 1940.
Source-derived case information.
- Parties
- Appellant: K. Sasidharan; Respondent: Kerala State Film Development Corporation
- Jurisdiction
- India
- Judgment Date
- 17 March 1994
- Procedural Posture
- Civil Appeal / Appeal From Division Bench Judgment of Kerala High Court
- Outcome
- Appeal dismissed
- Legal Topics
- Power of Court to Appoint Arbitrator, Interpretation of Arbitration Clauses, Exclusion of Arbitration Agreement
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
K. Sasidharan
Appellant
Kerala State Film Development Corporation
Respondent
Procedural Posture
Civil Appeal / Appeal From Division Bench Judgment of Kerala High Court
Legal Issues
- 1 Whether there was an arbitrable agreement under the contract for reference to arbitration
- 2 Whether clause 73 of Madras Detailed Standard Specifications or clause 12 of General Conditions of Contract were applicable
Ratio Decidendi
Since the arbitration clause was expressly excluded from the contract, clause 73 of MDSS does not apply and there is no arbitrable agreement between the parties. The Civil Court cannot appoint an arbitrator under Section 20 of the Arbitration Act, 1940.
Court Disposition
Appeal dismissed
Orders
- No costs
Full Case Text
Judgment text and source record
69 paragraphs
)
-
A
B
K. SASIDHARAN v. KERALA STATE FILM DEVELOPMENT CORPORATION
MARCH 17, 1994
(K. RAMASWAMY AND N. VENKATACHALA, J.J.]
Arbitration Act, 1940: Section 20.
Power of Court to appoint Arbitrator-Contract excluding arbitration C c/ause-Court-Wliether can appoint Arbitrator-Clause 73 of Madras Detailed standard Specification-Clause 12 of General Conditions of the Contract-Whether applicable.
The appellant entered into a contract with the Respondent-Corpora tion for construction of a theatre. During the execution of the contract a D dispute arose and the appellant filed an application under Section 20 of the Arbitration Act, 1940 for reference to an Arbitrator which was con tested by the respondent on the ground that there was no arbitrable agreement. The Trial Court appointed an Arbitrator holding that clause 73 of the Madras Detailed Standard Specifications (MDSS) which con- tained an arbitrable clause was applicable to the dispute. On appeal, a Division Bench of the High Court reversed the Trial Court's order.
E
'
In appeal to this Court, it was contended on behalf of the appellant that all items of work referred to in clause 12 of the General Conditions of the Contract include MDSS in addenda volume. Therefore, clause 73 of
F MDSS got attracted to the dispute.
Dismissing the ap1ieal, this Courts
HELD: 1. The High Court is right in its conclusion that there is no arbitrable agreement for reference to the Arbitrator. Therefore, the Civil Court cannot exercise its power under Section 20 of the Act to appoint an Arbitrator. [86-B]
G
2. The appellant and the respondent having specifically excluded the arbitration clause in the Contract, by necessary implication they excluded the clause 73 in MDSS. When the parties to the agreement, in terms of the H documents, have not incorporated the arbitration agreement in clause 73
82
' I
SASIDHARAN v. FILM DEVL. CORPN.
83
of MDSS, it cannot, by implication, be imported by interpretation that the A terms of clause 73 including arbitration cluase therein stands attracted. By necessary implication, it conflicts with the expressly agreed terms of the contract. Thereby, it is manifest that what the terms in the MDSS, referred to in clause 12 is only of the terms referable to the execution of the work, etc. and not one concerned with an agreement to refer any B dispute arising between the parties to an Arbitrator at a later point of time, or during the course of the execution of the work or after the completion thereof of any dispute arising between the parties in relation to the contract. [85-F -H; 86-A]
3. An arbitration clause in a contract, stands apart from rest of the C
contract; it must be construed according to its language and in the light of the circumstances in which it was made. [85-E]
Russell on Arbitration, 19th Edn. p.27, referred to.
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4022 of D
1994 .
•
From the Judgment and Order dated 15.12.86 of the Kerala High
Court in M.F.A. No. 460 of 1986. ',
G. Viswanatha Iyer, Dilip Pillai and E.M.S. Anam for the Appellant. E
A.T.M. Sampath for the Respondent.
The following Order of the Court was delievered :
Leave granted. Heard both the counsel.
F
The appellant had cin January 27, 1982 had entered into a contract with the respondent to construct a theatre. He completed the work and handed over the same to the respondent in May. 1985. During the execu tion of the contract a dispute had arisen on certain items of the work which was sought to be decided by arbitration. The appellant, therefore, filed 0.S. G No. 20 of 1986 in the Court of Subordinate Judge, Trivandrum under s. 20 of the Arbitration Act, 1940, for short 'the Act' for reference to an Arbitrator. The respondent contended that there is no arbitrable agree ment under the contract. Over-ruling the objection, the Subordinate Judge by his order dated June 5, 1986 held that clause 73 of the Madras Detailed H
84
SUPREME COURT REPORTS
[1994] 3 S.C.R.
A Standard Specifications for short MOSS would apply to the dispute which contains an arbitrable clasue and, therefore, by order dated 2nd July, 1986 appointed a retired District Judge as an Arbitrator. On appeal by the respondent in M.F.A. No. 460 of 1986, by order dated December 15, 1986, the Division Bench of the Kerala High Court held that clause 73 of MDSS is inapplicable. There is no arbitrable agreement for reference to the Arbitrator. Thus, this appeal by special leave.
B
Sri E.M.S. anam, learned counsel for the appellant, placing reliance on clasue 12 of the "General Condition of the Contract" contended that all items of work referred to therein would include MOSS in the addenda C volume. Clause 73 of the arbitrable agreement therein gets attracted to the dispute. Therefore, the trial court was right in its conclusion that the dispute is arbitrable under clause 73. The High Court was not right in its centra conclusion.
D
Having given our anxious consideration, we find that the contention raised by the appellant is not tenable. Admittedly, the contract contains Article 60 which provides "arbitration of any dispute or difference between the parties to the contract either during the progress or after completion of the works or the interpretation of the contract or as any matter or thing arising thereunder except as to the matters left to the sole cliscreti0n of the E Corporation Engineer under the clauses of the contract". While entering into the contract this clause was admittedly excluded. In Article 2 of the "General Conditions of the Contract" clause (b) provides that "the Original Agreement, with its accompanying Schedules form part of the Contract Documents and shall be kept by the Corporation but the Contractor shall F be supplied with a copy of the agreement and copies of Tender Notifica tion, General Conditions of the Contract, specifications, Drawings and relevant schedules all duly attested by the Contractor and the Managing Director". Clause (f) postulates that "the terms of the Contract cannot be added to, varied or reduced by any oral agreement previous or subsequent to its signature".
G
Clause 12 relied upon by Sri Anam, the relevant part reads thus : ''And item of work shall be carried out as per Madras Detailed Standard Specifications and its addenda volume and shall be deemed to have been included here". What clause 12 postualtes is that the General conditions regarding the execution of the work will be as carried on ·in accordance
H
'
'
SASIDHARAN v. FILM DEVL. CORPN.
85
B
with the conditions etc. contained in MOSS and addenda. General Condi- A tions of the Contract provided the accepted rates, units, tentative quantities etc. which were given in the Schedule A and the time schedules for the work was given in Schedule B. The list and details regarding supply of. drawings were given in Schedule C. The ·short description given in the schedule A for different items were only the General specifications. There after, the above 12th clause has been added, namely, "All items of work shall be carried out as per Madras Detailed Standard Specifications and its addenda volume and shall be deemed to have been included here." The arbitration agreement is colateral to the substantial stipuiation of the contract. It is merely procedural and ancillary to the contract and it is a mode of settling the disputes, though the agreement to do so is itself subject C to the discretion of the Court. Arbitration is distinguishable from other clauses in the contract. The other clauses set out the obligations which the parties have undertaken towards each other binding them, but the arbitra- tion clause does not impose on one of the parties an obligation towards the other. It embodies an agreement of both parties with consensus ad idem D that if any dispute arises with regard to the obligations undertaken therein which one party has undertaken towards the other, such a dispute shall be settled by a Tribunal of their own constitution. Therefore, arbitration clause in a contract, stands apart from rest of the contract, it must be construed according to its language and in the light of the circumstances in which it was made. Russell on Arbitration, 19th Edition, p.27 states that E na court cannot make a contract between the parties. In general its power would appear to end with interpretation. It applies equally to the estab lishment of an arbitration agreement 11
•
The appellant and the respondent having specifically excluded the F
arbitration clause in the contract, by necessary implication they exclused the clause 73 in MOSS. If it were to be contra it must expressly and specifically be incorporated in the contract which admittedly was not done. When the parties to the agreement, in terms of the documents, have not incorporated the arbitration agreement in clause 73 of MOSS, it cannot, by implication, be imported by interpretation that the terms of clause 73 G including arbitration clause therein stands attracted. By necessary implica tion, it conflicts with the expressly agreed terms of the contract. Thereby, it is manifest that what the terms in the MOSS, referred to in Clause 12 is only of the terms referable to the execution of the work, etc. and not one concerned with an agreement to refer any dispute arising between the H
-
86
'
SUPREME COURT REPORTS
[1994] 3 S.C.R.
A parties to an arbitration, at a later point of time, or during the course of the execution of the work or after the completion thereof any dispute arising between the parties in relation to the contract.
Therefore, the High Court is right in its conclusion that there is no arbitrable agreement for reference to the Arbitrator. The Civil Court in the circumstances cannot exercise its power under s. 20 of the Act to appoint an arbitrator and refer the dispute for arbitration.
B
The appeal is accordingly dismissed. No costs.
T.N.A.
Appeal dismissed.
·~