KANPUR ELECTRICITY SUPPLY CO. LTD. & ANR. versus M/S. L.M.L. LIMITED & ORS.
KESCO's insistence on a bank guarantee and refusal to accept the Bond, despite agreements, regulatory approval, and compliance by the respondent company, was unjustified and negated the rehabilitation efforts for a sick industrial unit. The relief undertaking and BIFR directions required flexible application of the Supply Code, and petitioner’s rigid approach obstructed respondent’s revival.
- Parties
- Petitioner: Kanpur Electricity Supply Co. Ltd.; Respondent: L.M.L. Limited
- Jurisdiction
- India
- Judgment Date
- 07 May 2010
- Procedural Posture
- SLP (civil) No. 33984 of 2009 / Supreme Court: Special Leave Petition
- Outcome
- Special Leave Petition dismissed
- Legal Topics
- Load Reduction, Contracted Load, Relief Undertaking, Sick Industrial Companies, Supply Code Compliance
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Kanpur Electricity Supply Co. Ltd.
Petitioner
L.M.L. Limited
Respondent
Procedural Posture
SLP (civil) No. 33984 of 2009 / Supreme Court: Special Leave Petition
Legal Issues
- 1 Whether KESCO was justified in refusing reduction of contracted electricity load from 8 MVA to 1.25 MVA despite agreement and compliance by respondent company.
- 2 Whether insistence on bank guarantee under amended Clause 4.49 was lawful despite respondent company's financial status and BIFR directions.
Ratio Decidendi
KESCO's insistence on a bank guarantee and refusal to accept the Bond, despite agreements, regulatory approval, and compliance by the respondent company, was unjustified and negated the rehabilitation efforts for a sick industrial unit. The relief undertaking and BIFR directions required flexible application of the Supply Code, and petitioner’s rigid approach obstructed respondent’s revival.
Court Disposition
Special Leave Petition dismissed
Orders
- No interference with the High Court order
- Petitioner-Company is not prevented from taking appropriate steps against the Respondent-Company if instalment payments or current electricity bills are defaulted
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment