MADHYA PRADESH POWER MANAGEMENT CO. LTD. & ANR. M/S DHAR WIND POWER PROJECTS PVT. LTD. & ORS. versus M/S DHAR WIND POWER PROJECTS PVT. LTD. & ORS.
The applicable tariff for the first respondent's project is governed by the actual date of commissioning, evidenced by SLDC data showing power injection occurred on 1 April 2016; the Tariff Order dated 17 March 2016 applies at Rs 4.78 per unit, and the project is entitled to parity of treatment with other projects commissioned during that control period. Orders of the High Court directing PPA at the higher tariff are set aside.
- Parties
- Appellant: Madhya Pradesh Power Management Co. Ltd.; Respondent: M/S Dhar Wind Power Projects Pvt. Ltd.; Respondent: Others
- Jurisdiction
- India
- Judgment Date
- 25 July 2019
- Procedural Posture
- Civil Appeal / Final Decision on Appeals
- Outcome
- Appeals partly allowed; impugned High Court orders set aside
- Legal Topics
- Tariff Determination, Power Purchase Agreement, Regulatory Commission Orders, Commissioning Criteria, Control Period, Parity of Treatment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Madhya Pradesh Power Management Co. Ltd.
Appellant
M/S Dhar Wind Power Projects Pvt. Ltd.
Respondent
Others
Respondent
Procedural Posture
Civil Appeal / Final Decision on Appeals
Legal Issues
- 1 Whether the first respondent's wind power project was commissioned before or after 1 April 2016
- 2 Which tariff order applies to the first respondent's project
- 3 Whether the High Court was correct in directing execution of PPA at the higher tariff
Ratio Decidendi
The applicable tariff for the first respondent's project is governed by the actual date of commissioning, evidenced by SLDC data showing power injection occurred on 1 April 2016; the Tariff Order dated 17 March 2016 applies at Rs 4.78 per unit, and the project is entitled to parity of treatment with other projects commissioned during that control period. Orders of the High Court directing PPA at the higher tariff are set aside.
Court Disposition
Appeals partly allowed; impugned High Court orders set aside
Orders
- First respondent entitled to benefit of Tariff Order dated 17 March 2016 (Rs 4.78/unit for 25 years)
- Appellants to process application for execution of a PPA on that basis with effect from 1 April 2016
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment