MAHANADI COALFIELDS LTD. & ORS. versus M/S. DHANSAR ENGINEERING CO. PVT. LTD. & ANR.
Clause 5 empowered appellant to increase quantity by 30% while contract was subsisting. Contractor was obliged to complete extra work within the contract or extended period. Respondents breached obligation by not completing balance work, becoming liable to compensate appellants for financial loss occasioned by engagement of third party at higher rate. Notice requirement under Clause 5 applied only to daily capacity increases, not merely extra quantity. Contractor may make representation to company to seek waiver or modification of penalty under contract terms.
- Parties
- Appellant: Mahanadi Coalfields Ltd. & Ors.; Respondent: M/s. Dhansar Engineering Co. Pvt. Ltd. & Anr.
- Jurisdiction
- India
- Judgment Date
- 27 September 2016
- Procedural Posture
- Civil Appeal / Supreme Court Appeal From High Court Judgment
- Outcome
- Appeal partly allowed; High Court judgment set aside.
- Legal Topics
- Variation of Contract Quantity, Work Contract, Contractual Obligations, Penalty Clause, Extension of Contract Period
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Mahanadi Coalfields Ltd. & Ors.
Appellant
M/s. Dhansar Engineering Co. Pvt. Ltd. & Anr.
Respondent
Procedural Posture
Civil Appeal / Supreme Court Appeal From High Court Judgment
Legal Issues
- 1 Whether Clause 5 empowered the company to increase extra quantity during subsistence of contract
- 2 Liability of contractor to complete extra work within extended contract period
- 3 Entitlement of company to penalize contractor for breach and recover financial loss
Ratio Decidendi
Clause 5 empowered appellant to increase quantity by 30% while contract was subsisting. Contractor was obliged to complete extra work within the contract or extended period. Respondents breached obligation by not completing balance work, becoming liable to compensate appellants for financial loss occasioned by engagement of third party at higher rate. Notice requirement under Clause 5 applied only to daily capacity increases, not merely extra quantity. Contractor may make representation to company to seek waiver or modification of penalty under contract terms.
Court Disposition
Appeal partly allowed; High Court judgment set aside.
Orders
- Respondents may make representation to appellants for waiver/modification of penalty under contract.
- Appellants may recover difference in contract rate and actual cost incurred for completion via third party from respondents, along with lawful interest.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment