MAHANADI COALFIELDS LTD. & ORS. versus M/S. DHANSAR ENGINEERING CO. PVT. LTD. & ANR.

MAHANADI COALFIELDS LTD. & ORS. versus M/S. DHANSAR ENGINEERING CO. PVT. LTD. & ANR.

Clause 5 empowered appellant to increase quantity by 30% while contract was subsisting. Contractor was obliged to complete extra work within the contract or extended period. Respondents breached obligation by not completing balance work, becoming liable to compensate appellants for financial loss occasioned by engagement of third party at higher rate. Notice requirement under Clause 5 applied only to daily capacity increases, not merely extra quantity. Contractor may make representation to company to seek waiver or modification of penalty under contract terms.

Parties
Appellant: Mahanadi Coalfields Ltd. & Ors.; Respondent: M/s. Dhansar Engineering Co. Pvt. Ltd. & Anr.
Jurisdiction
India
Judgment Date
27 September 2016
Procedural Posture
Civil Appeal / Supreme Court Appeal From High Court Judgment
Outcome
Appeal partly allowed; High Court judgment set aside.
Legal Topics
Variation of Contract Quantity, Work Contract, Contractual Obligations, Penalty Clause, Extension of Contract Period

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Legal principles 3 Authorities cited 9 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Mahanadi Coalfields Ltd. & Ors.

Appellant

M/s. Dhansar Engineering Co. Pvt. Ltd. & Anr.

Respondent

Procedural Posture

Civil Appeal / Supreme Court Appeal From High Court Judgment

  1. 1 Whether Clause 5 empowered the company to increase extra quantity during subsistence of contract
  2. 2 Liability of contractor to complete extra work within extended contract period
  3. 3 Entitlement of company to penalize contractor for breach and recover financial loss

Ratio Decidendi

Clause 5 empowered appellant to increase quantity by 30% while contract was subsisting. Contractor was obliged to complete extra work within the contract or extended period. Respondents breached obligation by not completing balance work, becoming liable to compensate appellants for financial loss occasioned by engagement of third party at higher rate. Notice requirement under Clause 5 applied only to daily capacity increases, not merely extra quantity. Contractor may make representation to company to seek waiver or modification of penalty under contract terms.

Court Disposition

Appeal partly allowed; High Court judgment set aside.

Orders

  • Respondents may make representation to appellants for waiver/modification of penalty under contract.
  • Appellants may recover difference in contract rate and actual cost incurred for completion via third party from respondents, along with lawful interest.