MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. versus M/S. JSW STEEL LIMITED & ORS.

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. versus M/S. JSW STEEL LIMITED & ORS.

Captive consumers/captive users are not liable to pay the additional surcharge under Section 42(4) because Section 9 grants them a statutory right to generate and to open access for their own use without requiring permission from the State Commission, and Section 42(4) applies only where the State Commission permits...

Source-derived case information.

Parties
Appellant: Maharashtra State Electricity Distribution Co. Ltd.; Respondent: M/s JSW Steel Limited & Ors.
Jurisdiction
India
Judgment Date
10 December 2021
Procedural Posture
Civil Appeal Nos. 5074 5075 of 2019 / Appeal From Appellate Tribunal for Electricity to the Supreme Court; Final Judgment on Appeal
Outcome
Appeals dismissed
Legal Topics
Captive Generation, Open Access, Additional Surcharge, Section 9, Electricity Act, 2003, Section 42(4)
Electricity Law Regulatory Law Captive Generation Open Access Additional Surcharge Section 9, Electricity Act, 2003 Section 42(4), Electricity Act, 2003

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Maharashtra State Electricity Distribution Co. Ltd.

Appellant

M/s JSW Steel Limited & Ors.

Respondent

Procedural Posture

Civil Appeal Nos. 5074 5075 of 2019 / Appeal From Appellate Tribunal for Electricity to the Supreme Court; Final Judgment on Appeal

  1. 1 Whether captive consumers/captive users are liable to pay additional surcharge under Section 42(4) of the Electricity Act, 2003
  2. 2 Interpretation of Section 9 and its interaction with Section 42(4) regarding open access and permission of State Commission

Ratio Decidendi

Captive consumers/captive users are not liable to pay the additional surcharge under Section 42(4) because Section 9 grants them a statutory right to generate and to open access for their own use without requiring permission from the State Commission, and Section 42(4) applies only where the State Commission permits consumers to receive supply from others.

Court Disposition

Appeals dismissed

Orders

  • The appeals are dismissed
  • No order as to costs