MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. versus M/S. DATAR SWITCHGEAR LIMITED & ORS.
The termination of contract by respondent No.2 was valid and justified due to a fundamental breach by the appellant in failing to supply necessary lists of locations for installation with no fault of respondent; respondent was ready and willing to perform, but prevented from doing so; the innocent party is entitled to damages for both the performed and unperformed portions of the contract; and mitigation is not required in these circumstances due to the custom nature of contract objects.
- Parties
- Appellant: Maharashtra State Electricity Distribution Company Ltd.; Respondent No.2: M/s. Datar Switchgear Limited; Respondents: Other Respondents
- Jurisdiction
- India
- Judgment Date
- 18 January 2018
- Procedural Posture
- Civil Appeal / Supreme Court Final Appeal From Division Bench Judgment
- Outcome
- Appeal dismissed with costs
- Legal Topics
- Termination of Contract, Arbitral Award, Damages, Fundamental Breach, Waiver
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Maharashtra State Electricity Distribution Company Ltd.
Appellant
M/s. Datar Switchgear Limited
Respondent No.2
Other Respondents
Respondents
Procedural Posture
Civil Appeal / Supreme Court Final Appeal From Division Bench Judgment
Legal Issues
- 1 Whether termination of contract by respondent was valid and justified
- 2 Entitlement to damages from contract termination
- 3 Mitigation of damages
Ratio Decidendi
The termination of contract by respondent No.2 was valid and justified due to a fundamental breach by the appellant in failing to supply necessary lists of locations for installation with no fault of respondent; respondent was ready and willing to perform, but prevented from doing so; the innocent party is entitled to damages for both the performed and unperformed portions of the contract; and mitigation is not required in these circumstances due to the custom nature of contract objects.
Court Disposition
Appeal dismissed with costs
Orders
- Appeal dismissed
- Costs imposed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment