MCDERMOTT INTERNTIONAL INC. versus BURN STANDARD CO. LTD. AND ORS.
Partial awards, though not named in the 1996 Act, are treated as interim awards and can be final for matters covered. Jurisdictional objections must be raised before arbitrator. Time was not of essence in this construction contract as evidence and conduct showed extension provisions and no timely objection. Quantification of damages can use accepted formulae; proof of actual damages required but not solely by invoice. Consequential damages exclusion in main contract does not bar direct claims under sub-contract. Substitution claim for heavier material not valid due to acceptance sub-silentio and ONGC's refusal of payment. Interest rate reduced to 7.5% due to long lapse of time. Exchange...
- Parties
- Appellant: MCDERMOTT INTERNATIONAL INC.; Respondent: BURN STANDARD CO. LTD.; Third Party: ONGC
- Jurisdiction
- India
- Judgment Date
- 12 May 2006
- Procedural Posture
- Application Under Section 34 of Arbitration and Conciliation Act, 1996 / Supreme Court Final Disposition of Challenge to Arbitral Awards
- Legal Topics
- Partial Award, Jurisdiction, Time Is Essence, Damages Quantification, Interest, Novation, Acceptance Sub Silentio, Consequential Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
MCDERMOTT INTERNATIONAL INC.
Appellant
BURN STANDARD CO. LTD.
Respondent
ONGC
Third Party
Procedural Posture
Application Under Section 34 of Arbitration and Conciliation Act, 1996 / Supreme Court Final Disposition of Challenge to Arbitral Awards
Legal Issues
- 1 Nature and validity of 'partial' awards under Arbitration and Conciliation Act, 1996
- 2 Jurisdictional objections to arbitral awards
- 3 Time being of essence in construction contracts
Ratio Decidendi
Partial awards, though not named in the 1996 Act, are treated as interim awards and can be final for matters covered. Jurisdictional objections must be raised before arbitrator. Time was not of essence in this construction contract as evidence and conduct showed extension provisions and no timely objection. Quantification of damages can use accepted formulae; proof of actual damages required but not solely by invoice. Consequential damages exclusion in main contract does not bar direct claims under sub-contract. Substitution claim for heavier material not valid due to acceptance sub-silentio and ONGC's refusal of payment. Interest rate reduced to 7.5% due to long lapse of time. Exchange...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment