MP RURAL ROAD DEVELOPMENT AUTHORITY & ANR. versus M/S. L.G. CHAUDHARY ENGINEERS & CONT.
The provisions of the Madhya Pradesh Arbitration Tribunal Act, 1983 are special and saved by Section 2(4) of the Arbitration and Conciliation Act, 1996, thus, disputes concerning execution of works contracts must be referred to the Tribunal under the MP Act, 1983. However, disputes relating to termination or cancellation of the works contract are not included under the MP Act's definition, and thus may be referred to an arbitrator appointed under the Arbitration and Conciliation Act, 1996. Due to divergence of views, the matter is referred to a larger bench.
- Parties
- Appellant: MP Rural Road Development Authority; Respondent: M/S. L.G. Chaudhary Engineers & Cont.
- Jurisdiction
- India
- Judgment Date
- 24 January 2012
- Procedural Posture
- Civil Appeal / Referred to Larger Bench
- Outcome
- Matter referred to larger Bench
- Legal Topics
- Statutory Arbitration Vs Contractual Arbitration, Repugnancy Under Article 254(2) of Constitution, Jurisdiction of Arbitration Tribunal, Interpretation of Works Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
MP Rural Road Development Authority
Appellant
M/S. L.G. Chaudhary Engineers & Cont.
Respondent
Procedural Posture
Civil Appeal / Referred to Larger Bench
Legal Issues
- 1 Whether the Madhya Pradesh Arbitration Tribunal Act, 1983 continues to operate for Works Contract disputes after the enactment of the Arbitration and Conciliation Act, 1996
- 2 Whether disputes arising from cancellation or termination of works contracts fall within the ambit of 'works contract' under Section 2(i) of the MP Act, 1983
- 3 Whether Section 7 of MP Act, 1983 mandates reference of disputes to the Tribunal irrespective of arbitration agreement
Ratio Decidendi
The provisions of the Madhya Pradesh Arbitration Tribunal Act, 1983 are special and saved by Section 2(4) of the Arbitration and Conciliation Act, 1996, thus, disputes concerning execution of works contracts must be referred to the Tribunal under the MP Act, 1983. However, disputes relating to termination or cancellation of the works contract are not included under the MP Act's definition, and thus may be referred to an arbitrator appointed under the Arbitration and Conciliation Act, 1996. Due to divergence of views, the matter is referred to a larger bench.
Court Disposition
Matter referred to larger Bench
Orders
- Judgment of High Court set aside, but due to divergence of views, matter placed before Chief Justice for constituting larger Bench.
- No order as to costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment