M/S C & C CONSTRUCTIONS LTD. versus IRCON INTERNATIONAL LTD.

M/S C & C CONSTRUCTIONS LTD. versus IRCON INTERNATIONAL LTD.

Clause 49.5 of the General Conditions of Contract, on its plain reading, bars claims for damages or compensation where delay is due to the Employer/Engineer and limits the remedy to grant of reasonable extension(s) of time; the appellant availed the extension remedy under clause 49, gave written undertakings not to claim anything other than escalation, and thereafter sought damages contrary to those undertakings; clause 49.5 was not waived by the respondent; given the limited scope of appellate interference under Section 37 (coextensive with Section 34 grounds), the Division Bench correctly upheld the arbitral tribunal and dismissed the appeal.

Parties
Appellant: M/s C & C Constructions Ltd.; Respondent: IRCON International Ltd.
Jurisdiction
India
Judgment Date
31 January 2025
Procedural Posture
Civil Appeal Under Section 37 of the Arbitration and Conciliation Act, 1996 / Judgment on Appeal by the Supreme Court (final Disposition)
Outcome
Appeal dismissed.
Legal Topics
Appeal Under Section 37 of the Arbitration and Conciliation Act, Scope of Interference in Arbitral Award Challenges, Limitation of Liability Clauses, Estoppel by Conduct/undertaking, Extension of Time in Construction Contracts, General Conditions of Contract Clause 49.5

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Legal principles 3 Authorities cited 12 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

M/s C & C Constructions Ltd.

Appellant

IRCON International Ltd.

Respondent

Procedural Posture

Civil Appeal Under Section 37 of the Arbitration and Conciliation Act, 1996 / Judgment on Appeal by the Supreme Court (final Disposition)

  1. 1 Whether clause 49.5 of the General Conditions of Contract bars the contractor from claiming damages or compensation for delay attributable to the Employer/Engineer
  2. 2 Whether clause 49.5 was waived by the respondent
  3. 3 Whether the Arbitral Tribunal erred in rejecting claims without allowing the appellant to lead evidence

Ratio Decidendi

Clause 49.5 of the General Conditions of Contract, on its plain reading, bars claims for damages or compensation where delay is due to the Employer/Engineer and limits the remedy to grant of reasonable extension(s) of time; the appellant availed the extension remedy under clause 49, gave written undertakings not to claim anything other than escalation, and thereafter sought damages contrary to those undertakings; clause 49.5 was not waived by the respondent; given the limited scope of appellate interference under Section 37 (coextensive with Section 34 grounds), the Division Bench correctly upheld the arbitral tribunal and dismissed the appeal.

Court Disposition

Appeal dismissed.

Orders

  • Appeal dismissed
  • Impugned judgment and order of the Division Bench of the High Court dated 01.03.2021 upheld