M/S. MSK PROJECTS (I) (JV) LTD versus STATE OF RAJASTHAN & ANR.
The Supreme Court held that District Judge and High Court erred by considering an issue not raised before the arbitral tribunal. Contractor was entitled to collect toll fee from Bharatpur-Deeg section as it was part of the project. Claim for compensation for non-execution of phase II was unjustified, as appellant had not invested for that phase. Appeals disposed, contractor entitled only to Rs. 26.34 lakhs for delay in issuing notification with 10% interest.
- Parties
- Appellant: MSK Projects (I) (JV) Ltd; Respondent: State of Rajasthan; Respondent: Another Respondent
- Jurisdiction
- India
- Judgment Date
- 21 July 2011
- Procedural Posture
- Civil Appeal / Supreme Court Decision on Appeal From High Court
- Outcome
- Appeals disposed of.
- Legal Topics
- Delay in Government Notification, Scope of Concession Agreement, Collection of Toll Fee, Arbitral Tribunal Jurisdiction, Award of Interest, Compensatory Nature of Toll, Breach and Compensation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
MSK Projects (I) (JV) Ltd
Appellant
State of Rajasthan
Respondent
Another Respondent
Respondent
Procedural Posture
Civil Appeal / Supreme Court Decision on Appeal From High Court
Legal Issues
- 1 Whether it was mandatory/necessary under the agreement/pre-bid understanding for the State to issue a notification barring vehicles through Bharatpur city
- 2 Whether the contractor had a right to collect toll fee on the Bharatpur-Deeg patch of the road
- 3 Whether the rate of interest could be reduced from 18% to 10% by the courts below
Ratio Decidendi
The Supreme Court held that District Judge and High Court erred by considering an issue not raised before the arbitral tribunal. Contractor was entitled to collect toll fee from Bharatpur-Deeg section as it was part of the project. Claim for compensation for non-execution of phase II was unjustified, as appellant had not invested for that phase. Appeals disposed, contractor entitled only to Rs. 26.34 lakhs for delay in issuing notification with 10% interest.
Court Disposition
Appeals disposed of.
Orders
- Matter remitted to arbitral tribunal to determine entitlement regarding Bharatpur-Deeg section and effect of non-execution of phase II.
- Contractor entitled only to Rs.26.34 lakhs for delay in notification, with 10% interest.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment