OIL AND NATURAL GAS CORPORATION LTD. versus THE PRESIDENT, OIL FIELD EMPLOYEES ASSOCIATION & ORS.

OIL AND NATURAL GAS CORPORATION LTD. versus THE PRESIDENT, OIL FIELD EMPLOYEES ASSOCIATION & ORS.

The High Court and this Court upheld the Tribunal's factual finding that the 19 September 2016 Memorandum of Settlement was primarily between contractors and their workmen (with ONGC only consenting) and therefore did not bind the workmen represented by the respondent unions who had claimed to be in reality...

Source-derived case information.

Parties
Appellant: Oil and Natural Gas Corporation Ltd.; Respondent: The President, Oil Field Employees Association; Respondent: Maharashtra Sanghatit Asanghatit Kamgar Sabha; Respondent: Maharashtra Employees Union; Respondent in Person: Shaligram G. Mishra
Jurisdiction
India
Procedural Posture
Civil Appeal / Final Judgment
Outcome
Appeal dismissed; impugned judgment of the Bombay High Court dated 30.01.2020 sustained.
Legal Topics
Jurisdiction of Industrial Tribunal, Binding Effect of Settlements Under Section 18(3)(d), Status of Contract Labour, Fair Wage Policy (fwp), Remittal to Tribunal and Implementation of Awards, Writ Jurisdiction
Industrial Law Labour and Employment Jurisdiction of Industrial Tribunal Binding Effect of Settlements Under Section 18(3)(d) Status of Contract Labour Fair Wage Policy (fwp) Remittal to Tribunal and Implementation of Awards Writ Jurisdiction

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 21 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Oil and Natural Gas Corporation Ltd.

Appellant

The President, Oil Field Employees Association

Respondent

Maharashtra Sanghatit Asanghatit Kamgar Sabha

Respondent

Maharashtra Employees Union

Respondent

Shaligram G. Mishra

Respondent in Person

Procedural Posture

Civil Appeal / Final Judgment

  1. 1 Whether the Central Government Industrial Tribunal had jurisdiction to adjudicate disputes where workmen were engaged through contractors but claimed to be employees of ONGC
  2. 2 Whether the Memorandum of Settlement dated 19 September 2016 (FWP) signed by contractors and certain unions is binding on the workmen represented by the respondent unions under Section 18(3)(d) of the Industrial Disputes Act, 1947
  3. 3 Whether the settlement of 19 September 2016 was a fair and just settlement and susceptible to being treated as binding where it allegedly required withdrawal of other proceedings

Ratio Decidendi

The High Court and this Court upheld the Tribunal's factual finding that the 19 September 2016 Memorandum of Settlement was primarily between contractors and their workmen (with ONGC only consenting) and therefore did not bind the workmen represented by the respondent unions who had claimed to be in reality employees of ONGC; the jurisdictional objection was a mixed question of fact and law not properly raised before the tribunal and the Tribunal's factual conclusion that the settlement was not a fair and binding settlement was supported by evidence and not perverse; consequently the Tribunal's directives, as modified by the High Court, were reasonable and the appeal was dismissed.

Court Disposition

Appeal dismissed; impugned judgment of the Bombay High Court dated 30.01.2020 sustained.

Orders

  • Appeal dismissed
  • Impugned judgment and order of the High Court dated 30.01.2020 is sustained