SONU BABU BHAMBID & ORS. versus DREAM DEVELOPERS & ORS.
Eligibility certificate is a prerequisite for enforcement of the agreement under which appellants sought rehabilitation; in its absence, the agreement terminated and no enforceable right to interim injunction existed. Additional evidence not raised before the lower courts cannot be admitted at this stage without proper procedure.
- Parties
- Appellant: Sonu Babu Bhambid & Ors.; Respondent: Dream Developers & Ors.
- Jurisdiction
- India
- Judgment Date
- 21 July 2009
- Procedural Posture
- Civil Appeal / Supreme Court Appeal From High Court Appellate Order Dismissing Appeal From City Civil Court's Refusal of Interim Injunction
- Outcome
- Appeal dismissed with costs.
- Legal Topics
- Interim Injunction, Slum Rehabilitation, Eligibility Certificate, Production of Additional Evidence
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sonu Babu Bhambid & Ors.
Appellant
Dream Developers & Ors.
Respondent
Procedural Posture
Civil Appeal / Supreme Court Appeal From High Court Appellate Order Dismissing Appeal From City Civil Court's Refusal of Interim Injunction
Legal Issues
- 1 Whether interim injunction should be granted restraining construction on CTS No.82 where appellants failed to obtain eligibility certificate and the area was not declared a slum area
- 2 Whether appellants could enforce the agreement without eligibility certificate
- 3 Whether production of additional document (letter dated 8.05.2009) was permissible at Supreme Court stage
Ratio Decidendi
Eligibility certificate is a prerequisite for enforcement of the agreement under which appellants sought rehabilitation; in its absence, the agreement terminated and no enforceable right to interim injunction existed. Additional evidence not raised before the lower courts cannot be admitted at this stage without proper procedure.
Court Disposition
Appeal dismissed with costs.
Orders
- Appeal dismissed with costs assessed at Rs. 10,000/- to the respondents.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment