SECTOR 14 RESIDENTS WELFARE ASSOCIATION AND ORS. versus STATE OF DELHI AND ORS.
The Supreme Court accepted the final report of the P.K. Kaul Committee regarding upgradation of sewerage systems in the trans-Yamuna and NOIDA areas. The Court directed that the Environment Pollution (Prevention and Control) Authority, chaired by Shri Bhure Lal, shall monitor and enforce the implementation of the...
Source-derived case information.
- Parties
- Petitioner: Sector 14 Residents Welfare Association and Others; Respondent: State of Delhi and Others
- Jurisdiction
- India
- Judgment Date
- 16 November 1998
- Procedural Posture
- Writ Petition (civil) / Order on Directions During Pendency (pending Matter)
- Outcome
- Directions issued for monitoring and implementation; case to remain pending for further directions.
- Legal Topics
- Sewerage System Upgradation, Environmental Protection, Monitoring of Court Directed Plans, Implementation of Action Plans
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sector 14 Residents Welfare Association and Others
Petitioner
State of Delhi and Others
Respondent
Procedural Posture
Writ Petition (civil) / Order on Directions During Pendency (pending Matter)
Legal Issues
- 1 Whether the sewerage management systems in the specified areas require upgradation and oversight?
- 2 Who are the authorities responsible for implementation and accountability for the action plan devised for upgradation of the sewerage system?
- 3 What should be the monitoring mechanism for ensuring the timely implementation of the action plan?
Ratio Decidendi
The Supreme Court accepted the final report of the P.K. Kaul Committee regarding upgradation of sewerage systems in the trans-Yamuna and NOIDA areas. The Court directed that the Environment Pollution (Prevention and Control) Authority, chaired by Shri Bhure Lal, shall monitor and enforce the implementation of the action plan within the prescribed timeframes and issue directions as necessary. Heads of named organisations are accountable for compliance, and directions issued by the Bhure Lal Committee are binding subject to orders of the Court.
Court Disposition
Directions issued for monitoring and implementation; case to remain pending for further directions.
Orders
- Copies of the Supreme Court's order and committee reports to be provided to the Environment Pollution (Prevention and Control) Authority.
- Authority to monitor and ensure implementation of the action plan as per schedule and issue directions to responsible organisations.
Full Case Text
Judgment text and source record
77 paragraphs
SECTOR 14 RESIDENTS WELFARE ASSOCIATION AND ORS.
11. STATE OF DELHI AND ORS.
NOVEMBER 16, 1998
[B.N. KIRPAL, S.P. KURDUKAR AND V.N. KHARE, JJ.]
A
B
Environmental Law----Sewerage system-Upgradation of-Constitution of Committee by Supreme Court-Report submitted by Committee-Action Plan for the works required to be undertaken suggested by Committee-Time frame for implementation of Report-Directions by Supreme Court- C Environment Pollution (Prevention and Control) Authority shall monitor the implementation of the Committee's Report-Said Authority shall ensure that works mentioned in the Action Plan are undertaken as per Schedule Authority can issue appropriate directions to persons responsible for implementing different items of work.
D
CIVIL ORIGINAL JURISDICTION : Writ Petition (C)·No. ?14 of
1996.
Under Article 32 of the Constitution of India.
A.K. Goyal, Additional Advocate General, A.K. Ganguli (A.C.) and P.P. E
Malhotra, Shiv Sagar Tiwari, Ashok Srivastava, Ms. Sushma Suri, D.S. Mehra, G.B. Sathe, Ms. Niti Dikshit, Pradeep Misra, Ms. Binu Tamta, Vijay Panjwani, V.B. Saharya and A.D.N. Rao for the appearing parties.
The following Order of the Court was delivered :
F
In respect of the upgradation of sewerage management systems in the trans-Yamuna area of Delhi and Sectors 14, 14-A, 15, ISA, 16, 16-A and 17 ofNOIDA this writ petition was filed in this Court. By Order dated 6 January, 1998 this Court constituted a Committee of five persons headed by Shri P.K. Kaul, former Cabinet Secretary as its Chairman to examine all the issues in G detail and to submit a report.
The Committee submitted its interim report on 5th March, 1998. In October 1998 the said Committee has submitted its final report relating to status and options for upgradation of the sewerage management systems in the aforesaid areas.
695
H
696
A
SUPREME COURT REPORTS [1998] SUPP. 2 S.C.R.
Copies of the said report were given to the learned counsel for the
parties and no objection to the same has been received.
We have gone through the report and, in our opinion, it merits acceptance. Apart from indicating the status of the system as of today, the said report at pages 40-44 gives the action plan for the works which are B required to be undertaken and the organisations responsible for undertaking each work. At page 44 the Committee has drawn up a time frame with regard to the various activities mentioned in the action plan.
As per the action plan suggested by the Committee, the authorities who C are responsible for the implementation thereof have been mentioned. The persons who can be held accountable in respect thereof are as under :
Name of the Authority
Person Accountable
I. Delhi Jal Board
(i) Chairman; and
D
2 Delhi Flood Control &
Irrigation Department
E 3. Municipal Corporation
of Delhi
(ii) Member Secretary
Chief Secretary, Delhi
Chairman
4. Delhi Development Authority
Vice-Chairman
5. U.P. Pollution Control Board
Chairman
F 6. G.D.A.
7. Delhi Pollution Control Board
8. NOIDA Administration
G 9. U.P. Jal Nigam
10. U.P. Industrial Development
Corporation
Vice-Chairman
Chairman
Chairman
Chairman
Chairman
11. Min. of Urban Development
H
Govt.ofNCT of Delhi
Chief Secretary, Delhi.
SECTOR 14RESIDENTSWELFAREASSOCIATIONv. STATE
697
As already noticed, the time frame which has been suggested mentions A
that activities at Sr. Nos. 1-9 of the action plan should be completed before 31st December 1998, the activities at Sr. Nos.10-22 are to be completed before 31st March, 1999, the activities at Sr. Nos. 23 & 24 are to be completed before 30th September, 1999 and activities at Sr. Nos. 25 to 34 are to be completed before 31st March, 2000.
B
We see no reason to change the time frame except that as far as activities Nos. I to 9 are concerned, we extend the time for completing the same by 31st January, 1999.
The Central Government had under section 3 of the Environment C
Protection Act constituted an Environment Pollution (Prevention and Control) Authority under the Chairmanship of Shri Bhure Lal. It will be appropriate that the monitoring of the implementation of P.K. Kaul Committee's report in the manner indicated in the action plan of the said report is undertaken by the s~id Bhure Lal Committee which is a statutory committee having powers to issue directions. We, therefore, direct that copies of this Order as well as of D the interim and final report of the P.K. Kaul Committee be forwarded within a week to Shri Bhure Lal with a direction that the said Committee will ensure that various works mentioned in the action plan are undertaken as per schedule. The Committee will have full authority to issue appropriate directions to the various organisations who have been mentioned as being responsible for E implementing different items of works as per the action plan. The Bhure Lal Committee will also examine the recommendations contained in paragraphs 5.1, 8.6 and 8.7 and other relevant paragraphs of the said report and issue such ordets or directions as it may deem fit and proper.
It is made clear that if any organisation fails in carrying out the directions F
so issued the persons mentioned as being accountable will have to satisfy this Court as to why appropriate action should not be taken for non implementation of the directions issued. If for any reason any of these authorities are not in a position to implement or carry out any of the directions so issued, liberty is granted to approach this Court in this behalf. Subject to G any orders which may be passed by this Court the directions given by Bhure Lal Committee shall be final and binding on all. Copies of the reports and this order be also sent to the aforesaid organisations.
To come up for further directi.:ms in February, 1999. Spare copies of the report of the P.K. Kaul Committee shall be filed in the Registry by the Delhi H
•
698
SUPREME COURT REPORTS [1998] SUPP. 2 S.C.R.
A Administration within one week and the Registry shall forward the copies of the report of P. K. Kaul committee and this order to the respective organisations within one week thereafter.
T.NA.
Petition still pending.
(
•