STATE OF KARNATAKA BY ITS CHIEF SECRETARY versus P. K. SINHA AND ANR.

STATE OF KARNATAKA BY ITS CHIEF SECRETARY versus P. K. SINHA AND ANR.

The corrected draft scheme is in conformity with the Supreme Court's judgment and Section 6A of the Inter-State River Water Disputes Act, 1956 and must be taken forward for notification and implementation without further delay. No further contempt action is necessary as the scheme's formulation and changes satisfy...

Source-derived case information.

Parties
Applicant: State of Karnataka by its Chief Secretary; Respondent: State of Tamil Nadu by its Chief Secretary; Respondent: Union of India; Respondent: State of Kerala; Respondent: Union Territory of Puducherry; Respondent: P.K. Sinha and Anr.; Applicant: R.K.R. Anantaraman
Jurisdiction
India
Procedural Posture
Contempt Petition (civil) / Final Disposal of Contempt Petitions and Interlocutory Applications
Outcome
All interlocutory applications, miscellaneous applications and the contempt petitions are disposed of.
Legal Topics
Cauvery River Water Allocation, Implementation of Tribunal Award, Section 6 a Scheme, Constitution Seventh Schedule Entry 17
Inter State Water Disputes Cauvery River Water Allocation Implementation of Tribunal Award Section 6 a Scheme Constitution Seventh Schedule Entry 17

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

State of Karnataka by its Chief Secretary

Applicant

State of Tamil Nadu by its Chief Secretary

Respondent

Union of India

Respondent

State of Kerala

Respondent

Union Territory of Puducherry

Respondent

P.K. Sinha and Anr.

Respondent

R.K.R. Anantaraman

Applicant

Procedural Posture

Contempt Petition (civil) / Final Disposal of Contempt Petitions and Interlocutory Applications

  1. 1 Non-framing of the scheme within the time granted by Supreme Court
  2. 2 Appropriateness of clauses in the Draft Scheme
  3. 3 Extent of Central Government's power to modify Tribunal recommendations

Ratio Decidendi

The corrected draft scheme is in conformity with the Supreme Court's judgment and Section 6A of the Inter-State River Water Disputes Act, 1956 and must be taken forward for notification and implementation without further delay. No further contempt action is necessary as the scheme's formulation and changes satisfy the Court's directions and address parties' objections, which are found meritless.

Court Disposition

All interlocutory applications, miscellaneous applications and the contempt petitions are disposed of.

Orders

  • The corrected draft scheme is accepted and must be taken forward, notified in Official Gazette and implemented promptly.
  • No further contempt action is necessary.