M/S SAI BABA SALES PVT. LTD. versus UNION OF INDIA
The Supreme Court endorsed the NGT’s protection of the already completed construction: the four constructed buildings are to be treated as being under a valid Environmental Clearance granted by the PCMC on 28.11.2017 (the competent authority at the relevant time), applying the doctrine of legitimate expectation because the Project Proponent acted in accordance with the prevailing regime and made substantial investments; however, any further construction requires fresh clearance from the competent authority as per the currently applicable framework.
- Parties
- Appellant / Project Proponent: M/S Sai Baba Sales Pvt. Ltd.; Respondent: Union of India; Original Applicant / Respondent: Original Applicant (Pune resident, respondent No.10)
- Jurisdiction
- India
- Judgment Date
- 26 November 2021
- Procedural Posture
- Civil Appeal Under Section 22 of the National Green Tribunal Act, 2010 / Disposed by Supreme Court Judgment Dated 26.11.2021
- Outcome
- Appeals disposed of; Supreme Court endorsed NGT's protection of completed construction and imposed conditions on further construction
- Legal Topics
- Environmental Clearance, Environmental Impact Assessment (eia) Notification, Doctrine of Legitimate Expectation, Validity of Environmental Clearance
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
M/S Sai Baba Sales Pvt. Ltd.
Appellant / Project Proponent
Union of India
Respondent
Original Applicant (Pune resident, respondent No.10)
Original Applicant / Respondent
Procedural Posture
Civil Appeal Under Section 22 of the National Green Tribunal Act, 2010 / Disposed by Supreme Court Judgment Dated 26.11.2021
Legal Issues
- 1 Whether the Project Proponent possessed a valid Environmental Clearance under the EIA notification dated 14.9.2006 and subsequent notifications
- 2 Effect of the MoEFCC notification dated 9.12.2016 and the NGT judgment dated 8.12.2017 on ECs granted by local authorities (PCMC) in the interregnum
- 3 Whether the doctrine of legitimate expectation protects already completed construction carried out on the basis of EC obtained from the competent authority of the relevant time
Ratio Decidendi
The Supreme Court endorsed the NGT’s protection of the already completed construction: the four constructed buildings are to be treated as being under a valid Environmental Clearance granted by the PCMC on 28.11.2017 (the competent authority at the relevant time), applying the doctrine of legitimate expectation because the Project Proponent acted in accordance with the prevailing regime and made substantial investments; however, any further construction requires fresh clearance from the competent authority as per the currently applicable framework.
Court Disposition
Appeals disposed of; Supreme Court endorsed NGT's protection of completed construction and imposed conditions on further construction
Orders
- The four constructed buildings are to be treated as being under a valid Environmental Clearance granted on 28.11.2017 by the Pimpri Chinchwad Municipal Corporation and to have all legal consequences thereof
- The Project Proponent shall not undertake any further construction on the strength of the EC dated 28.11.2017; any further construction requires fresh clearance from the competent authority under the currently applicable framework
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment