NARMADA BACHAO ANDOLAN ETC. ETC. versus UNION OF INDIA AND ORS.
The court held that the decision to construct the dam was a government policy based on expert assessment and long-term development needs, and absent violation of law or malafide, judicial review cannot supplant government discretion. Relief, rehabilitation, and environmental concerns have been provided for by the Tribunal's award and monitored by authorities; the court's role is limited to ensuring implementation. Environmental clearance, although initially granted when studies were incomplete, was conditional and subject to ongoing assessment and compliance; thus, it cannot be considered invalid. The Public Interest Litigation jurisdiction does not extend to changing lawfully made policy...
- Parties
- Petitioner: Narmada Bachao Andolan; Respondent: Union of India and Others
- Jurisdiction
- India
- Judgment Date
- 18 October 2000
- Procedural Posture
- Writ Petition / Final Judgment
- Outcome
- Writ petition dismissed by majority; court upholds dam construction with directions for relief and rehabilitation monitoring.
- Legal Topics
- Public Interest Litigation, Judicial Review, Dam Construction Policy, Relief and Rehabilitation, Environmental Clearance, Water Disputes, Resettlement of Oustees
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Narmada Bachao Andolan
Petitioner
Union of India and Others
Respondent
Procedural Posture
Writ Petition / Final Judgment
Legal Issues
- 1 Whether the court can interfere with government policy decisions such as construction of the Sardar Sarovar Dam.
- 2 Whether adequate relief, rehabilitation, and environmental measures for project oustees have been taken in accordance with law.
- 3 Validity of the environmental clearance granted to the dam project despite studies being incomplete.
Ratio Decidendi
The court held that the decision to construct the dam was a government policy based on expert assessment and long-term development needs, and absent violation of law or malafide, judicial review cannot supplant government discretion. Relief, rehabilitation, and environmental concerns have been provided for by the Tribunal's award and monitored by authorities; the court's role is limited to ensuring implementation. Environmental clearance, although initially granted when studies were incomplete, was conditional and subject to ongoing assessment and compliance; thus, it cannot be considered invalid. The Public Interest Litigation jurisdiction does not extend to changing lawfully made policy...
Court Disposition
Writ petition dismissed by majority; court upholds dam construction with directions for relief and rehabilitation monitoring.
Orders
- States must ensure completion of relief and rehabilitation for oustees at every 5 meter stage of dam height increase, certified by Grievance Redressal Authorities.
- Work on further dam construction shall not proceed until environmental clearance is granted by an Expert Committee constituted as per 1994 Environmental Impact Assessment Notification.
Full Case Text
Judgment text and source record