McCabe Builders(Dubllin) Ltd -v- Sagamu Developments Ltd & ors [2009] IESC 31 (01 April 2009)
A binding contract existed between McCabes and Sagamu Developments Limited, the terms of which are set out in the RIAI Articles of Agreement and Conditions of Contract 2002 (Revision 1, Print 4) as signed, together with the letter of 5th August 2005 (signed by both parties) and the documents referred to and incorporated therein. The Bill of Approximate Quantities forms part of the contract to the extent that it is incorporated by reference through the August correspondence and the parties' course of dealing, notwithstanding the RIAI form's exclusion of quantities except as a schedule of rates. The parties' clear intention to be bound by a formal contract and their conduct override the...
- Citation
- [2009] IESC 31
- Parties
- Plaintiff/respondent: McCabe Builders (Dublin) Limited; Defendant/appellant: Sagamu Developments Limited; Defendant/appellant: Laragan Developments Limited; Defendant/appellant: Hanly Group Limited
- Jurisdiction
- Ireland
- Judgment Date
- 01 April 2009
- Procedural Posture
- Civil Appeal / Supreme Court Appeal From High Court Decision
- Outcome
- Appeal allowed; High Court order set aside
- Legal Topics
- Formation of Contract, Interpretation of Contract Documents, Tender Process, Quantum Meruit, Rectification, Standard Form Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
McCabe Builders (Dublin) Limited
Plaintiff/respondent
Sagamu Developments Limited
Defendant/appellant
Laragan Developments Limited
Defendant/appellant
Hanly Group Limited
Defendant/appellant
Procedural Posture
Civil Appeal / Supreme Court Appeal From High Court Decision
Legal Issues
- 1 Whether a binding contract existed between the parties for the construction project
- 2 Whether the Bill of Approximate Quantities formed part of the contract documents
- 3 Whether the RIAI standard form contract excluded the Bill of Approximate Quantities except as a schedule of rates
Ratio Decidendi
A binding contract existed between McCabes and Sagamu Developments Limited, the terms of which are set out in the RIAI Articles of Agreement and Conditions of Contract 2002 (Revision 1, Print 4) as signed, together with the letter of 5th August 2005 (signed by both parties) and the documents referred to and incorporated therein. The Bill of Approximate Quantities forms part of the contract to the extent that it is incorporated by reference through the August correspondence and the parties' course of dealing, notwithstanding the RIAI form's exclusion of quantities except as a schedule of rates. The parties' clear intention to be bound by a formal contract and their conduct override the...
Court Disposition
Appeal allowed; High Court order set aside
Orders
- Declaration that a binding contract exists between McCabes and Sagamu Developments Limited on the terms of the signed RIAI contract, the August 2005 letter, and incorporated documents as set out in the counterclaim.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment