John A. Wood Ltd. v. Kerry County Council [1997] IEHC 168 (31st October, 1997)

John A. Wood Ltd. v. Kerry County Council [1997] IEHC 168 (31st October, 1997)

The planning permission was ineffective due to non-compliance with conditions precedent, the application for extension was not made within the prescribed time, and substantial works were not carried out within the appropriate period. The Planning Authority's refusal to extend the permission was justified under the...

Source-derived case information.

Citation
[1997] IEHC 168
Parties
Respondent: County Council of the County of Kerry; Applicant: John Wood Limited/John A. Wood Limited
Jurisdiction
Ireland
Procedural Posture
Judicial Review and Section 27 Application / Final Judgment
Outcome
Application dismissed
Legal Topics
Duration of Planning Permission, Extension of Planning Permission, Compliance With Planning Conditions, Unauthorised Development
Planning Law Administrative Law Duration of Planning Permission Extension of Planning Permission Compliance With Planning Conditions Unauthorised Development

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

County Council of the County of Kerry

Respondent

John Wood Limited/John A. Wood Limited

Applicant

Procedural Posture

Judicial Review and Section 27 Application / Final Judgment

  1. 1 Whether the planning permission was effective given non-compliance with conditions precedent
  2. 2 Whether the application for extension of planning permission was made within the prescribed time
  3. 3 Whether substantial works were carried out within the appropriate period

Ratio Decidendi

The planning permission was ineffective due to non-compliance with conditions precedent, the application for extension was not made within the prescribed time, and substantial works were not carried out within the appropriate period. The Planning Authority's refusal to extend the permission was justified under the statutory framework.

Court Disposition

Application dismissed

Orders

  • Order in the Judicial Review proceedings to discharge the order of Flood J. dated 27th July, 1995 and dismiss the application.
  • Order in the Section 27 application in terms of paragraph numbers 1, 2 and 3 of the Notice of Motion.