Aga Khan v. Firestone [1991] IEHC 3; [1992] ILRM 31 (25th July, 1991)
A binding verbal contract was concluded between Aga Khan and Firestones on 27 November 1989, confirmed by the letter of 1/4 December 1989, which satisfied the Statute of Frauds. Akazawa's first refusal option was voluntary, unsupported by consideration, and unenforceable. The right of first refusal did not constitute an interest in land. Aga Khan is entitled to specific performance; Akazawa is entitled to damages only.
- Citation
- [1992] ILRM 31
- Parties
- Plaintiff: Karim Aga Khan; Defendant: Bertram R. Firestone; Defendant: Diana M. J. Firestone; Plaintiff: Yoshika Akazawa
- Jurisdiction
- Ireland
- Procedural Posture
- Civil / High Court Judgment
- Outcome
- Aga Khan's claim for specific performance granted; Akazawa's claim for specific performance denied; Akazawa entitled to damages.
- Legal Topics
- Specific Performance, Statute of Frauds, First Refusal Option, Consideration, Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Karim Aga Khan
Plaintiff
Bertram R. Firestone
Defendant
Diana M. J. Firestone
Defendant
Yoshika Akazawa
Plaintiff
Procedural Posture
Civil / High Court Judgment
Legal Issues
- 1 Whether a verbal contract for sale of land was concluded between Aga Khan and Firestones on 27 November 1989
- 2 Whether the letter of 1/4 December 1989 constitutes a sufficient note or memorandum under the Statute of Frauds
- 3 Whether Akazawa's first refusal option is enforceable
Ratio Decidendi
A binding verbal contract was concluded between Aga Khan and Firestones on 27 November 1989, confirmed by the letter of 1/4 December 1989, which satisfied the Statute of Frauds. Akazawa's first refusal option was voluntary, unsupported by consideration, and unenforceable. The right of first refusal did not constitute an interest in land. Aga Khan is entitled to specific performance; Akazawa is entitled to damages only.
Court Disposition
Aga Khan's claim for specific performance granted; Akazawa's claim for specific performance denied; Akazawa entitled to damages.
Orders
- Order for specific performance of contract in favour of Aga Khan against Firestones.
- Closing date for contract fixed at six months from judgment date.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment