Killerk Ltd -v- Shane Houlihan [2009] IEHC 358 (16 July 2009)
The plaintiff is entitled to judgment for the contractual sum as the architect's certificate of practical completion was issued and is binding. The contract does not exclude the right of set-off, so the defendant's cross-claim arising from the same contract entitles him to an equitable set-off, to be determined by...
Source-derived case information.
- Citation
- [2009] IEHC 358
- Parties
- Plaintiff: Killerk Limited; Defendant: Shane Houlihan
- Jurisdiction
- Ireland
- Judgment Date
- 16 July 2009
- Procedural Posture
- Commercial Summary Judgment and Stay Application / High Court Judgment on Summary Judgment and Stay Pending Arbitration
- Outcome
- Judgment for the plaintiff with partial stay on execution and registration pending arbitration of the defendant's cross-claim.
- Legal Topics
- Summary Judgment, Arbitration Clause Enforcement, Equitable Set Off, Architect's Certificate, Cross Claim, Stay of Execution
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Killerk Limited
Plaintiff
Shane Houlihan
Defendant
Procedural Posture
Commercial Summary Judgment and Stay Application / High Court Judgment on Summary Judgment and Stay Pending Arbitration
Legal Issues
- 1 Whether the plaintiff is entitled to summary judgment for the final payment under a construction contract despite the defendant's cross-claim
- 2 Whether the proceedings should be stayed and referred to arbitration under the contract's arbitration clause
- 3 Whether the defendant is entitled to an equitable set-off against the plaintiff's claim
Ratio Decidendi
The plaintiff is entitled to judgment for the contractual sum as the architect's certificate of practical completion was issued and is binding. The contract does not exclude the right of set-off, so the defendant's cross-claim arising from the same contract entitles him to an equitable set-off, to be determined by arbitration. Judgment is entered for the plaintiff, but execution and registration are stayed in respect of the amount corresponding to the defendant's actual expenditure on remedial works pending arbitration.
Court Disposition
Judgment for the plaintiff with partial stay on execution and registration pending arbitration of the defendant's cross-claim.
Orders
- Judgment entered for €1,475,580 in favour of the plaintiff.
- Stay on execution and registration in respect of €244,116 pending arbitration outcome.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment