Mc Cabe Builders (Dublin) Ltd -v- Sagamu Developments Ltd & Ors [2007] IEHC 391 (23 November 2007)
No concluded contract existed as to the essential terms, specifically regarding whether the Bill of Quantities formed part of the contract documents and how variations were to be treated. The parties' minds did not meet on these fundamentals, and the signed 'blue form' RIAI contract excluded the Bill of Quantities as a contract document. Therefore, the plaintiff is entitled to payment on a quantum meruit basis for work done.
- Citation
- [2007] IEHC 391
- Parties
- Plaintiff: McCabe Builders (Dublin) Limited; Defendant: Sagamu Developments Limited; Defendant: Laragan Developments Limited; Defendant: Hanly Group Limited
- Jurisdiction
- Ireland
- Judgment Date
- 23 November 2007
- Procedural Posture
- Commercial Court Contract Dispute / Judgment
- Outcome
- Declaration that no concluded contract existed as to the essential terms; plaintiff entitled to quantum meruit.
- Legal Topics
- Formation of Contract, Interpretation of Contract, Building Contracts, Quantum Meruit, Variation Claims
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
McCabe Builders (Dublin) Limited
Plaintiff
Sagamu Developments Limited
Defendant
Laragan Developments Limited
Defendant
Hanly Group Limited
Defendant
Procedural Posture
Commercial Court Contract Dispute / Judgment
Legal Issues
- 1 Whether a binding contract was concluded between the parties and, if so, its terms
- 2 Whether the Bill of Quantities formed part of the contract documents
- 3 How variations and extra works are to be treated for payment purposes
Ratio Decidendi
No concluded contract existed as to the essential terms, specifically regarding whether the Bill of Quantities formed part of the contract documents and how variations were to be treated. The parties' minds did not meet on these fundamentals, and the signed 'blue form' RIAI contract excluded the Bill of Quantities as a contract document. Therefore, the plaintiff is entitled to payment on a quantum meruit basis for work done.
Court Disposition
Declaration that no concluded contract existed as to the essential terms; plaintiff entitled to quantum meruit.
Orders
- Plaintiff entitled to be paid on a quantum meruit basis for work done.
- Matter of quantum to be determined by arbitration if not agreed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment