Seahound Wind Developments LTD v Mid Clare Renewable Energy DAC (Approved) [2024] IEHC 371 (20 June 2024)
Plaintiff fulfilled contractual obligations relating to payment, including provision of vouching for Cahermurphy Transformer costs; defendant failed to establish a bona fide defence that payment was contingent on provision of further documentation, as no evidence was provided that defendant's bank required such documents. Calculation of late payment interest was adequately explained and correctly applied statutory rate. Judgment for plaintiff for €32,835.13.
- Citation
- [2024] IEHC 371
- Parties
- Plaintiff: Seahound Wind Developments LTD; Defendant: Mid Clare Renewable Energy DAC
- Jurisdiction
- Ireland
- Judgment Date
- 20 June 2024
- Procedural Posture
- Summary Judgment Application / Judgment on Application
- Outcome
- judgment for plaintiff
- Legal Topics
- Late Payment Interest, Summary Judgment, Contractual Interpretation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Seahound Wind Developments LTD
Plaintiff
Mid Clare Renewable Energy DAC
Defendant
Procedural Posture
Summary Judgment Application / Judgment on Application
Legal Issues
- 1 Entitlement to statutory late payment interest under European Communities (Late Payment in Commercial Transactions) Regulations 2012
- 2 Whether payment obligations were contingent on provision of documentation
- 3 Adequacy of breakdown for liquidated sum claimed
Ratio Decidendi
Plaintiff fulfilled contractual obligations relating to payment, including provision of vouching for Cahermurphy Transformer costs; defendant failed to establish a bona fide defence that payment was contingent on provision of further documentation, as no evidence was provided that defendant's bank required such documents. Calculation of late payment interest was adequately explained and correctly applied statutory rate. Judgment for plaintiff for €32,835.13.
Court Disposition
judgment for plaintiff
Orders
- Judgment entered for plaintiff in amount of €32,835.13.
- Matter listed for mention to finalise orders and costs on 26 June 2024 at 10.30am.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment