Brandley & anor -v- Deane & anor [2016] IECA 54 (02 March 2016)

Brandley & anor -v- Deane & anor [2016] IECA 54 (02 March 2016)

The cause of action for negligence and breach of contract in property damage cases accrues when actual damage occurs, not merely when negligent conduct takes place. The plaintiffs did not suffer actionable damage at the time of installation of the defective foundations; damage occurred when cracks appeared in December 2005, within the limitation period.

Citation
[2016] IECA 54
Parties
Plaintiff/appellant: Liam Brandley; Plaintiff/appellant: WJB Developments Limited; Defendant/respondent: Hubert Deane t/a Hubert Deane & Associates; Defendant/respondent: John Lohan t/a John Lohan Ground Works Contractors
Jurisdiction
Ireland
Judgment Date
02 March 2016
Procedural Posture
Appeal / Judgment on Appeal
Outcome
appeal allowed
Legal Topics
Statute of Limitations, Negligence, Accrual of Cause of Action, Property Damage

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Liam Brandley

Plaintiff/appellant

WJB Developments Limited

Plaintiff/appellant

Hubert Deane t/a Hubert Deane & Associates

Defendant/respondent

John Lohan t/a John Lohan Ground Works Contractors

Defendant/respondent

Procedural Posture

Appeal / Judgment on Appeal

  1. 1 When does the cause of action accrue for negligence and breach of contract in property damage cases?
  2. 2 Is the test for accrual based on discoverability or occurrence of actionable damage?

Ratio Decidendi

The cause of action for negligence and breach of contract in property damage cases accrues when actual damage occurs, not merely when negligent conduct takes place. The plaintiffs did not suffer actionable damage at the time of installation of the defective foundations; damage occurred when cracks appeared in December 2005, within the limitation period.

Court Disposition

appeal allowed

Orders

  • High Court decision set aside
  • Matter remitted to High Court for assessment of damages