Mafa Moshoeshoe v District Football Association-Leribe and Others (LC/APN 3 of 2012) [2013] LSHC 48 (16 July 2013)

Mafa Moshoeshoe v District Football Association-Leribe and Others (LC/APN 3 of 2012) [2013] LSHC 48 (16 July 2013)

The applicant has established all requirements for a temporary interdict. The respondents, having been served with the application and certificate of urgency, continued construction to the applicant's prejudice. The court grants the interim interdict to preserve the status quo pending determination of the main case.

Source-derived case information.

Citation
[2013] LSHC 48
Parties
Applicant: Mafa Moshoeshoe; 1st Respondent: District Football Association - Leribe; 2nd Respondent: Lesotho Football Club; 3rd Respondent: Land Registrar; 4th Respondent: Commissioner of Lands; 5th Respondent: Land Administration Authority; 6th Respondent: Attorney General
Court
High Court
Jurisdiction
Lesotho
Case Number
LC/APN 3 of 2012
Procedural Posture
Originating Application (land Court) / Ruling on Interlocutory Application for Interim Interdict
Outcome
Interim interdict granted in favour of the applicant
Legal Topics
Interdicts, Land Ownership Dispute, Court Procedure
Source Language
en
Civil Procedure Land Law Interdicts Land Ownership Dispute Court Procedure

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 9 Party arguments 2
Sign in to unlock

Parties

Mafa Moshoeshoe

Applicant

District Football Association - Leribe

1st Respondent

Lesotho Football Club

2nd Respondent

Land Registrar

3rd Respondent

Commissioner of Lands

4th Respondent

Land Administration Authority

5th Respondent

Attorney General

6th Respondent

Procedural Posture

Originating Application (land Court) / Ruling on Interlocutory Application for Interim Interdict

  1. 1 Whether the applicant is entitled to an interim interdict restraining the respondents from continuing construction on the disputed plot pending determination of the main case
  2. 2 Whether the parties complied with the Land Court Rules in their pleadings

Ratio Decidendi

The applicant has established all requirements for a temporary interdict. The respondents, having been served with the application and certificate of urgency, continued construction to the applicant's prejudice. The court grants the interim interdict to preserve the status quo pending determination of the main case.

Court Disposition

Interim interdict granted in favour of the applicant

Orders

  • Respondents are interdicted and restrained forthwith from continuing with construction works or any other works on plot number 23123-275 (also known as 23123-475) at Ha ‘Mathata – Maputsoe, Leribe district.
  • Costs of the application are awarded to the applicant as provided under Rule 100 of the Land Court Rules.