Condonation was refused due to flagrant procedural breaches and lack of any explanation for delays; the appeal was dismissed regardless of the prospects of success.

Source-derived case information.

Citation
[1986] LSCA 28
Parties
Appellant: Michael Mthembu; Respondent: Lesotho Building Finance Corporation
Court
Court of Appeal
Jurisdiction
Lesotho
Case Number
C of A (CIV) 4 of 1984
Procedural Posture
Civil Appeal / Judgment on Condonation Application and Appeal
Outcome
appeal dismissed with costs
Legal Topics
Condonation, Appeal Procedure, Delay in Prosecution, Finality of Litigation
Source Language
en
Civil Procedure Condonation Appeal Procedure Delay in Prosecution Finality of Litigation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Michael Mthembu

Appellant

Lesotho Building Finance Corporation

Respondent

Procedural Posture

Civil Appeal / Judgment on Condonation Application and Appeal

  1. 1 Whether condonation for procedural non-compliance and delay should be granted to the appellant
  2. 2 Whether the appeal should be heard despite procedural breaches

Ratio Decidendi

Condonation was refused due to flagrant procedural breaches and lack of any explanation for delays; the appeal was dismissed regardless of the prospects of success.

Court Disposition

appeal dismissed with costs

Orders

  • Appeal dismissed with costs to the respondent.